100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

MBA 742 Final Comprehensive Resource To Help You Ace Includes Frequently Tested Questions With ELABORATED 100% Correct COMPLETE SOLUTIONS Guaranteed Pass First Attempt!! Current Update!!

Rating
-
Sold
-
Pages
32
Grade
A+
Uploaded on
06-01-2026
Written in
2025/2026

MBA 742 Final Comprehensive Resource To Help You Ace Includes Frequently Tested Questions With ELABORATED 100% Correct COMPLETE SOLUTIONS Guaranteed Pass First Attempt!! Current Update!! 1. Develop Schedule Process -ANSWER - The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model. 2. Planned Dates- ANSWER - Key benefit of the Develop Schedule process is that it generates for completing project activities. 3. Schedule Net- ANSWER -The techniques of identifying early and late start dates, as well as early and late finish dates, for the uncompleted portions of project schedule activities. 4. Critical Path - ANSWER - the sequence of activities the represents the longest path through the project, which determines the shortest possible duration 5. CPM (Critical Path Method) - ANSWER A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule module. 6. CCM (Critical Chain Method) - ANSWER A schedule method that allows the project team to place butters on any project schedule path to account for limited resources and project uncertainties. 7. CPM is focused on tasks and CCM focuses on the resourses 8. CPM is a task based model 9. CCM is a Resource based model 10. In order to determine the project's critical path, it is necessary to perform both a forward and backward pass through the network. 11. In CPM, a Forward pass will ID the early-start and early finish times. 12. In CPM, a Backward pass will ID the late-start and late-finish times.

Show more Read less











Whoops! We can’t load your doc right now. Try again or contact support.

Document information

Uploaded on
January 6, 2026
Number of pages
32
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

  • mba 742

Content preview

MBA 742 Final Comprehensive Resource To Help You Ace 2026-2027 Includes Frequently
Tested Questions With ELABORATED 100% Correct COMPLETE SOLUTIONS
Guaranteed Pass First Attempt!! Current Update!!

1. Develop Sched- The process of analyzing activity sequences, durations, resource requirements,
S
ule Process and schedule constraints to create the project schedule model.

2. Planned Dates Key benefit of the Develop Schedule process is that it generates for
completing project activities.

3. Schedule Net- The techniques of identifying early and late start dates, as well as early and late
work Analysis finish dates, for the uncompleted portions of project schedule activities.

4. Critical Path the sequence of activities the represents the longest path through the project,
which determines the shortest possible duration

5. CPM (Critical A method used to estimate the minimum project duration and determine the
Path Method) amount of scheduling flexibility on the logical network paths within the schedule
module.

6. CCM (Critical A schedule method that allows the project team to place butters on any project
Chain Method) schedule path to account for limited resources and project uncertainties.

7. tasks & resources CPM is focused on and CCM focuses on the .

8. task CPM is a based model

9. Resource CCM is a based model

10. Forward & Back- In order to determine the project's critical path, it is necessary to perform both a
ward and pass through the network.

11. Forward In CPM, a pass will ID the early-start and early finish times.

12. Backward In CPM, a pass will ID the late-start and late-finish times.

13. Forward Pass A critical path method technique for calculating the early start and early finish
dates by working forward through the schedule model from the project start date
or a given point in time.


, MBA 742 Final Comprehensive Resource To Help You Ace 2026-2027 Includes Frequently
Tested Questions With ELABORATED 100% Correct COMPLETE SOLUTIONS
Guaranteed Pass First Attempt!! Current Update!!


S14. Backward Pass A critical path method technique for calculating the late start and late finish dates
by working backward through the schedule model from the project end date.

15. Early Start (ES) In CPM, the earliest date the activity can start.

16. Early Finish (EF) In CPM, the earliest date the activity can finish

17. Late Finish (LF) In CPM, the latest date that the activity can finish without causing a delay to the
project completion date.

18. Late Start (LS) In CPM, the latest date that the activity can start without causing a delay to the
project completion date.

19. Free Float The amount of time that a schedule activity can be delayed without delaying the
early start date of any successor or violating a schedule constraint.

20. Total Float The amount of time that a schedule activity can be delayed or extended from its
early start date without delaying the project finish date or violating a schedule
constraint.

21. Critical A useful way of describing the critical path is as a continuous string(s) of
activities in the schedule between the start and finish of the project.

22. Duration The sum of the activity durations in the critical path is equal to the project's
; therefore a delay to any critical activity will result in a delay to the project
completion date.

23. Critical Activity An activity that is on the project's critical path. Does not possess any float, total
float = 0.

24. Flexibility The critical path method is used to calculate the amount of scheduling that
exists based on the parameters and known constraints entered into the model.

25.



, Schedule Flexibil- On any network path, this is measured by the amount of time that a schedule
ity activity can be delayed or extended from its early start date without delaying the
project finish date or violating a schedule constraint, and it is termed "total float"

26. zero The critical path in the model is normally characterized by total float for that
path

27. Critical Chain Developed from the critical path method and considers the ettects of resource al-
Method (CCM) location, resource optimization, resource leveling and activity duration uncertainty
on the critical path determined using the critical path method.

28. Buffers & buffer The critical chain method introduces the concept of and management
to account for limited resources and project uncertainties.

29. Critical Chain In CCM, the resource constrained critical path is known as the .

30. Critical Chain Components of using the CCM:
Method • Build a critical path network diagram.
• Apply resources and then identify the resource-limited schedule that may have
an altered critical path.
• Identify the "drum resource" that is the root cause of the resource-constrained
critical path.
• Identify the resource-constrained critical path as the critical chain.
• Add butters that are non-work schedule activities to manage uncertainty
• Determine the size of the butter based on uncertainty in duration of the chain of
dependent activities
• Plan for the latest possible start and finish dates and focus on managing butter
durations

31. Resources; cycle The critical chain approach attempts to address two major project management
goals:
1. Completing projects more quickly and funneling more projects through the




, organization with adding .
2. Reduce project time and deliver projects more quickly.

32. Longest The critical chain focuses on the sequence of activities through the project
and considers the logical and resource dependencies within a project.

33. The unavailabili- What commonly causes a project to slip?
ty of "critical" re-
sources.

34. Resource Level- A technique in which start and finish dates are adjusted based on resource
ing constraints with the goal of balancing demand for resources with the available
supply.

35. 1. What-if Scenar- Types of modeling techniques that can be used to help develop the schedule
ios Analysis
2. Simulation

36. What-if Scenarios The process of evaluating scenarios in order to predict their ettect on project
Analysis objectives.

37. Simulation Uses a project model that translates the uncertainties specified at a detailed level
into their potential impact on objectives that are expressed at the level of the total
project.

38. probability distri- Project simulations use computer models and estimates of risk, usually expressed
bution as a of possible costs or durations at a detailed work level, and are
typically performed using the Monte Carlo Analysis

39. Monte Carlo Sim- A process which generates hundreds or thousands of probable performance
ulation outcomes based on probability distributions for cost and schedule on individual
tasks. The outcomes are then used to generate a probability distribution for the
project as a whole.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
EWLindy Harvard University
View profile
Follow You need to be logged in order to follow users or courses
Sold
710
Member since
3 year
Number of followers
431
Documents
7425
Last sold
3 days ago
EN.CY.CLO.PE.DI.A

As a Career Tutor, I understand the pressure of managing demanding coursework, exams, and practical requirements across multiple disciplines. These professionally organized revision materials are designed to support students in nursing, healthcare administration, business, information systems, Engineering, health, IT, or trade courses management programs by simplifying complex concepts and reinforcing high-yield academic content. The materials are developed to help students: Understand core theories and practical applications across Multiple Disciplines Review exam relevant content aligned with undergraduate and graduate curriculam To Strengthen critical thinking, analytical reasoning, and decision-making skills Save time with clear, structured summaries instead of overwhelming textbooks Prepare efficiently for tests, assignments, case studies, and professional exams Each resource is created with academic standards in mind, integrating real world examples, industry terminology, and evidence based concepts commonly required in professional programs. Whether you are studying nursing fundamentals, healthcare management, information systems, project management, business strategy, Engineering these materials provide focused, reliable support for academic success. These revision guides are ideal for: Nursing and allied health students Healthcare administration and public health students Business, MBA, and management students Information technology and information systems students, engineering, business, IT, or trade courses If you are looking for clear, student-friendly, exam-focused revision materials that support multiple career pathways, these resources are designed to help you study smarter, perform better, and stay confident throughout your academic journey. WISH YOU SUCCESS!!

Read more Read less
3.8

107 reviews

5
55
4
13
3
16
2
6
1
17

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions