T/F: A major function of the DOT is to carry out Construction and Reconstruction programs to provide the public with adequate transportation service. - ANSWERSTrue For DOT management of construction and reconstruction projects includes the following specific responsibilities: A. Planning, Programming, and Design B. Contract Administrations C. Contractor Payments D. Design and Contract Management E. All of the above - ANSWERSE. All of the above T/F: To pay for work performed by contractors, progress and Final Estimates are needed? - ANSWERSTrue Which of the following is not officially considered a "Contract Document"? A. Supplemental Agreements and Work Orders B. Notebooks and Estimates Procedure Manual. C. Standard Specifications. D .Construction Manual. E. Answers B & D. - ANSWERSE. Answers B & D. Between printings of the Standard Specifications, what does the Department publish to identify and describe changes in the Specifications? A. CPAM B. Supplemental Specifications C. Work Orders D. Specification Changes - ANSWERSB. Supplemental Specifications Select the correct sequence of documents in order of precedence, with the document highest in authority listed first.

Show more Read less
Institution
Estimates Level 1
Course
Estimates Level 1









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Estimates Level 1
Course
Estimates Level 1

Document information

Uploaded on
January 3, 2026
Number of pages
14
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

FINAL ESTIMATES LEVEL 1 EXAM
QUESTIONS AND ANSWERS 2026
T/F: A major function of the DOT is to carry out Construction and Reconstruction
programs to provide the public with adequate transportation service. - ANSWERSTrue

For DOT management of construction and reconstruction projects includes the following
specific responsibilities:
A. Planning, Programming, and Design
B. Contract Administrations
C. Contractor Payments
D. Design and Contract Management
E. All of the above - ANSWERSE. All of the above

T/F: To pay for work performed by contractors, progress and Final Estimates are
needed? - ANSWERSTrue

Which of the following is not officially considered a "Contract Document"?
A. Supplemental Agreements and Work Orders
B. Notebooks and Estimates Procedure Manual.
C. Standard Specifications.
D .Construction Manual.
E. Answers B & D. - ANSWERSE. Answers B & D.

Between printings of the Standard Specifications, what does the Department publish to
identify and describe changes in the Specifications?
A. CPAM
B. Supplemental Specifications
C. Work Orders
D. Specification Changes - ANSWERSB. Supplemental Specifications

Select the correct sequence of documents in order of precedence, with the document
highest in authority listed first.
A. Contract Plans, Development Specifications, Standard Specifications, Special
Provisions, Technical Special Provisions, Supplemental Specifications, Design
Standards.
B. Design Standards, Special Provisions, Technical Special Provisions, Supplemental
Specifications, Contract Plans, development Specifications, Standard Specifications.
C. Special Provisions, Technical Special Provisions, Contract Plans, Design Standards,
Development Specifications, Supplemental Specifications, Standard Specifications.
D. Supplemental Specifications, Special Provisions, Contract Plans, Development
Specifications, Standards Specifications, Technical Special Provisions, Design
Standards.

, E. None of the above. - ANSWERSC. Special Provisions, Technical Special Provisions,
Contract Plans, Design Standards, Development Specifications, Supplemental
Specifications, Standard Specifications.

True or False. When checked and verified, final estimates serve as the basis for Final
Payment. - ANSWERSTrue

Which of the following sets for the Department's methods and Procedures for preparing
and checking final estimates?

A. Construction Inspection Mathematics
B. Project Engineer
C. Preparation and Documentation Manual
D. CPAM - ANSWERSC. Preparation and Documentation Manual

Please match the appropriate documentation name with the correct description below:
A. [Final Plans]: For reviewing contract time charges before clearing estimates for final
payment; [Computation Books]: Documents pertinent changes during construction and
show the "as-built' condition; [Field Books]: Contains alignment notes and cross section
notes, etc.
B. [Construction Diaries]: For reviewing contract time charges before clearing estimates
for final payment; [Final Plans]: Documents pertinent changes during construction and
show the "as-built' conditions; [Field Books]: Contains alignment notes and cross
section notes, etc.
C. [Final Plans]: For reviewing contract time charges before clearing estimates for final
payment; [Tabulation Forms]: Documents pertinent changes during construction and
show the "as-built' conditions; [Field Books]: Contains alignment notes and cross
section notes, etc.
D. [Final Plans]: For r - ANSWERSB. [Construction Diaries]: For reviewing contract time
charges before clearing estimates for final payment; [Final Plans]: Documents pertinent
changes during construction and show the "as-built' conditions; [Field Books]: Contains
alignment notes and cross section notes, etc.

When using calculators or computers, you should use the:

A. Rules of rounding described in CONSTRUCTION MATH.
B. Full decimal capabilities of the machine
C. CPAM as a guide to rounding
D. Machine only as a backup to your manual computations
E. None of the above - ANSWERSB. Full decimal capabilities of the machine

True or False. It is usually necessary to measure items which are to be paid for on a
Lump Sum or Plan Quantity basis. - ANSWERSFalse

True or False. To measure and pay for the work performed by Contractors, Progress
and Final Estimates are needed. - ANSWERSTrue

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
papersmaster01 Howard Community College
View profile
Follow You need to be logged in order to follow users or courses
Sold
285
Member since
2 year
Number of followers
106
Documents
14214
Last sold
14 hours ago
PAPERSMASTER01

On this page you will find documents , package deals, flashcards offered by seller PAPERSMASTER01.With our documents on your side you"ll be well equipped to tackle you exams and achieve the grades you need.

3.9

71 reviews

5
22
4
33
3
9
2
3
1
4

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions