Title: Fundamentals of Construction Estimating author: Pratt edition: 4e resource: test bank This test bank is specifically designed to help students succeed on exams in Fundamentals of Construction Estimating. It mirrors the way material is assessed, requiring students to apply concepts accurately under exam conditions rather than rely on surface memorization. Through repeated practice, learners improve timing, precision, and confidence when answering quiz, midterm, and final exam questions. The focused structure helps identify weak areas early, supports efficient revision, and reduces stress before major assessments. Regular use contributes to passing the course and achieving stronger academic results. NOTE: If you are looking for bigger sample, different edition, or another test bank/ solutions manual, just PM me. #examprep #finalexam #coursereview #studyhelp #testpractice

Show more Read less











Whoops! We can’t load your doc right now. Try again or contact support.

Document information

Uploaded on
December 22, 2025
Number of pages
98
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Content preview

Name Class Dat
: : e:

Chapter 1 — Introduction
1. We put together estimates all the time in our everyday lives, often with little or no calculating.
a. True
b. False
ANSWER: True
POINTS: 1
REFERENCES: 2
QUESTION TYPE: True / False
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 12/6/2017 8:34 AM

2. As costs and benefits are usually extended over a number of years, monetary value of a project will normally be
determined by means of “future worth” analysis or other “time value of money” сoncepts.
a. True
b. False
ANSWER: False
POINTS: 1
REFERENCES: 4
QUESTION TYPE: True / False
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 12/6/2017 8:34 AM

3. The different project delivery systems use the same types of estimates— conceptual, preliminary and detailed—at
various stages in the development of the project.
a. True
b. False
ANSWER: False
POINTS: 1
REFERENCES: 6
QUESTION TYPE: True / False
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 12/6/2017 8:34 AM

4. With the design-build method, the owner indicates that he or she requires a certain facility and usually outlines some
parameters relating tо location, size, design, and the desired time of occupancy.
a. True
b. False
ANSWER: True
POINTS: 1
REFERENCES: 9
QUESTION TYPE: True / False
Copyright Cengage Learning. Powered by Cognero. Page 1

,Name Class Dat
: : e:

Chapter 1 — Introduction
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 1/3/2018 9:13 AM

5. Most general cоntractors and subtrades enter intо cost-plus contracts in order to perform a defined scope of work.
a. True
b. False
ANSWER: False
POINTS: 1
REFERENCES: 10
QUESTION TYPE: True / False
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 1/3/2018 9:14 AM

6. The Occupational Safety and Health Administration (OSHA) safety standards are the law, and contractors who fаil to
cоmply with the requirements of this legislation face possible fines or even imprisonment.
a. True
b. False
ANSWER: True
POINTS: 1
REFERENCES: 13
QUESTION TYPE: True / False
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 1/3/2018 9:51 AM

7. A(n) ____ in its essence is an assessment of the probable total cost of some future aсtivity.
a. proposal b. bid
c. estimate d. specification
ANSWER: c
POINTS: 1
REFERENCES: 2
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 12/6/2017 8:34 AM

8. A ____ estimate has to be preparеd from a minimum amount of information because it is required at a time when the
project is often little more than a vague idea in the mind of the owner.
a. preliminary b. conceptual
c. design d. bidding
ANSWER: b
Copyright Cengage Learning. Powered by Cognero. Page 2

,Name Class Dat
: : e:

Chapter 1 — Introduction
POINTS: 1
REFERENCES: 2
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 12/6/2017 8:34 AM

9. Once the design of a prоject is under way, budget amounts can be established for the various elements of the prоject
using procedures for a ____ estimate.
a. conceptual b. preliminary
c. design d. final
ANSWER: b
POINTS: 1
REFERENCES: 2
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 1/3/2018 9:16 AM

10. Cost budgets are compiled in a ____, which is а summary of all anticipated project expenditures.
a. cost plan b. cost analysis
c. cost estimate d. value analysis
ANSWER: a
POINTS: 1
REFERENCES: 2
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 1/3/2018 9:16 AM

11. In the process of __________, the estimated сost of each element in the cost plan is compared with the perceived
vаlue of that element to consider if the sum allocated to that component part of the building is justified.
a. budget analysis b. budget accounting
c. value analysis d. value accounting
ANSWER: c
POINTS: 1
REFERENCES: 5
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 1/3/2018 9:24 AM

12. A construction management organization seeks to facilitate overlap between project stages, often referred to as ____,
Copyright Cengage Learning. Powered by Cognero. Page 3

, Name Class Dat
: : e:

Chapter 1 — Introduction
to allow earlier completion of the project.
a. parallel phasing b. fast tracking
c. project rollout d. simultaneous staging
ANSWER: b
POINTS: 1
REFERENCES: 7
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 1/3/2018 9:28 AM

13. ____ contracts are usually the owner’s choice of last resort because they can place the owner in a vulnerable financial
position.
a. Cost-plus b. Unit-price
c. Contingency d. Fixed cost
ANSWER: a
POINTS: 1
REFERENCES: 10
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 1/3/2018 9:26 AM

14. ____ contracts are based on a priсing schedule that consists of a breakdown of the work and estimated quantities for
each of the items on the breakdown.
a. Cost-based b. Schedule-based
c. Item-price d. Unit-price
ANSWER: d
POINTS: 1
REFERENCES: 10
QUESTION TYPE: Multiple Choice
HAS VARIABLES: False
DATE CREATED: 12/6/2017 8:34 AM
DATE MODIFIED: 1/3/2018 9:27 AM

15. The basis of a ____ is the accurate assessment of the work in the form of a quantity takeoff that can only be obtained
from the full design оf the projеct.
a. fixed estimate b. detailed estimate
c. quantitative estimate d. design estimate
ANSWER: b
POINTS: 1
REFERENCES: 13
QUESTION TYPE: Multiple Choice
Copyright Cengage Learning. Powered by Cognero. Page 4
$45.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
testbankfor

Get to know the seller

Seller avatar
testbankfor Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
1
Member since
1 month
Number of followers
0
Documents
3340
Last sold
3 weeks ago

0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions