01. You are working with your project team to identify the project activities within
your project. Which of the following is NOT a tool and technique that will be useful in
defining the project activities?
a) Decomposition
b) Rolling wave plan
c) Precedence diagramming method
d) Templates - ANS-Answer:
c) Precedence diagramming method
02. In which of the following group decision making techniques does the largest block
in a group decide the group decision even if a bulk is not achieved?
a) Majority
b) Unanimity
c) Dictatorship
d) Plurality - ANS-Answer: