In a one-machine system, the order in a. true
which Jons are processed has no effect on
total time to completion
a. true
b. false
In a one-time machine system, the shortest a. true
processing time sequencing rule performs
well to reduce overall job lateness
a. true
b. false
in a two-machine system, the order in which b. false
jobs are processed has no effect on total
time to completion
a. true
b. false
, SCMN 4770 Exam 3
which of the following are sequencing rules d. I, II, and III
used in practice?
I. first come/ first served
II. earliest due date
III. Least work remaining
a. I only
b. I and II only
c. I and III only
d. I, II, and III
Updating order due dates to reflect b. false
changes in conditions always improves
shop-flow performance.
a. True
b. False
production activity control pertains mainly a. true
to activities that take place in the MPC
engine.
a. true
b. false
, SCMN 4770 Exam 3
Productions activity control's main link with a. detailed capacity planning
the rest of the MPC system is
a. detailed capacity planning
b. detailed material planning
c. material and capacity plans
d. master production scheduling
the shop-floor system is kept current on b. false
changes to the material plan by the MRP
system.
a. true
b. false
Formal Shop-Floor control systems are b. false
necessary in a just-in-time (JIT) system.
a. true
b. false
vendor scheduling is critical in a JIT system. a. true
a. true
b. false