QUESTIONS AND CORRECT ANSWESR (VERIFIED
ANSWERS) PLUS RATIONALES 2025/2026 Q&A
|INSTANT DOWNLOAD PDF
1. What is the primary purpose of the Federal Acquisition Regulation (FAR)?
A. To provide a uniform set of rules for all government acquisitions
B. To allow contractors to bypass government rules
C. To dictate state-level procurement policies
D. To regulate private sector contracts
Correct answer: A – The FAR establishes a standardized framework for federal
procurement to ensure fairness, transparency, and compliance with federal laws.
2. Which type of contract places the most risk on the contractor?
A. Cost-reimbursement contract
B. Fixed-price contract
C. Time-and-materials contract
D. Letter contract
Correct answer: B – Fixed-price contracts require the contractor to deliver at the
agreed price regardless of costs, placing maximum financial risk on them.
3. Which of the following are considered contract types under FAR?
A. Fixed-price
B. Cost-reimbursement
,C. Incentive
D. All of the above
Correct answer: D – FAR recognizes multiple contract types, including fixed-price,
cost-reimbursement, and incentive contracts, each with different risk allocations.
4. What is a “simplified acquisition threshold” (SAT)?
A. The minimum value for government contracts
B. The threshold below which simplified procurement procedures can be used
C. The value above which sole-source contracts are required
D. A threshold only used in defense contracting
Correct answer: B – The SAT allows agencies to use streamlined procurement
procedures for contracts below a certain dollar value, simplifying administration.
5. What is required in a justifications and approvals (J&A) document?
A. Reason for using noncompetitive procurement
B. Identification of the contractor
C. Expected cost and performance justification
D. All of the above
Correct answer: D – A J&A explains why a contract is awarded without full
competition and includes rationale, contractor info, and estimated cost.
6. Which clause ensures that the contractor complies with equal employment
opportunity requirements?
A. Termination for convenience clause
B. Equal Opportunity Clause (EO Clause)
C. Changes clause
D. Inspection of work clause
,Correct answer: B – The EO Clause mandates contractor compliance with
nondiscrimination and equal employment policies in federal contracts.
7. What is the purpose of a performance-based acquisition?
A. To focus on how tasks are completed
B. To define measurable outcomes instead of processes
C. To eliminate contractor accountability
D. To reduce competition
Correct answer: B – Performance-based acquisitions emphasize results and
outcomes, giving contractors flexibility in methods while holding them accountable
for performance.
8. When can a contract be terminated for convenience?
A. Only when the contractor defaults
B. When the government decides to end the contract for any reason
C. Only after contractor approval
D. Never
Correct answer: B – Termination for convenience allows the government to end the
contract at any time, providing equitable adjustment to the contractor.
9. Which of the following are key factors in source selection?
A. Cost or price
B. Technical capability
C. Past performance
D. All of the above
Correct answer: D – Source selection evaluates multiple factors to ensure the
government selects the best value offeror.
, 10. What is an indefinite-delivery/indefinite-quantity (IDIQ) contract?
A. A contract with a fixed completion date and quantity
B. A contract providing for an indefinite number of deliveries within stated limits
C. A subcontract awarded by a prime contractor
D. A single-award contract with no modifications
Correct answer: B – IDIQ contracts provide flexibility by allowing the government
to order varying quantities as needs arise, within minimum and maximum limits.
11. Which clause allows the government to adjust contract terms if unforeseen
conditions occur?
A. Changes clause
B. Disputes clause
C. Termination clause
D. Payment clause
Correct answer: A – The Changes clause allows the government to direct
modifications within the scope of the contract, such as adjustments to
specifications or quantities.
12. When is a cost-reimbursement contract appropriate?
A. When precise costs are known and fixed
B. When uncertainty exists in scope, technical approach, or costs
C. For commercial off-the-shelf products
D. Only for sole-source contracts
Correct answer: B – Cost-reimbursement contracts protect the contractor from
unknown costs while incentivizing efficiency but require careful oversight.