Ques ons and answers Updated RATED A+ NEW
EDITION
One advantage of 100% inspec on over sampling
inspec on is that 100% inspec on
(A) provides more informa on about quality levels
(B) gives zero defects to the customer
(C) reduces the personal bias of the inspector
(D) requires less machine-operator training - Ans A provides more informa on about quality
levels
When the term "R & R" is applied to digital calipers, it
refers to
(A) removal and replacement
(B) rela vity and reproducibility
(C) repeatability and reliability
(D) repeatability and reproducibility - Ans D repeatability and reproducibility
The proper method of placing parts on a surface plate and then removing them is
(A) rotate on and slide off
(B) rotate on and li+ off
(C) set on and slide off
(D) set on and li+ off - Ans A rotate on and slide off
, Who is responsible for determining whether a follow-up response is sufficient to close out an
internal audit?
(A) Execu ve management
(B) The quality manager
(C) The audit team leader
(D) The internal auditee - Ans C The audit team leader
Which of the following methods is used to develop an exhaus ve list of ideas about a subject?
(A) Goal-se3ng
(B) Brainstorming
(C) Benchmarking
(D) Problem-solving - Ans B Brainstorming
A document that asserts that a product conforms to
specifica on is known as a cer ficate of
(A) qualifica on
(B) valida on
(C) calibra on
(D) compliance - Ans D compliance
Confidence limits are generated in order to define the
(A) limits of random varia on around a control value
(B) limits that contain all future observa ons
(C) interval within which a popula on parameter lies
(D) amount of varia on that the process exhibits - Ans C interval within which a popula on
parameter lies
, The purpose of a calibra on schedule is to
(A) detect deteriora on of accuracy
(B) meet ISO audit requirements
(C) test inspector performance
(D) increase product acceptance - Ans A detect deteriora on of accuracy
What is the percent yield for a normally distributed
process in which the item length specifica on is
5.750 ± 0.004, X is 5.752, and the standard devia on is
0.002 ?
(A) 15.73%
(B) 19.15%
(C) 47.72%
(D) 83.99% - Ans D 83.99%
In prepara on for construc on of a cause and effect
diagram, it is important to
(A) plot separate charts for each source
(B) focus only on what makes things go wrong
(C) record everything people suggest
(D) validate possible root causes - Ans C record everything people suggest
A quality technician uses a c chart to monitor the number of defects in a square foot of
material. A+er the ini al startup period, the mean number of defects is calculated at 13.5. What
should the control limits be for the c chart?
LCL UCL