Which clause is related to Acquisition?
Ans: 52.215 - Instructions to Offerors - Competitive Acquistion
What is considered a contract action?
Ans: Contract action means any oral or written action that results in the
purchase, rent, or lease of supplies or equipment, services, or
construction.
Who accepts the burden of latent defect?
Ans: The burden is on the government to prove that defective material
and workmanship was the probable cause of product failure or non-
conformance.
Who can you submit a claim to?
Ans: Contractor claims are submitted to the KO
,What is a claim?
Ans: a written demand or assertion by one of the contracting parties
seeking (i) payment of a specific sum of money, (ii) adjustment or
interpretation of contract terms, or (iii) other relief arising under or
relating to the contract.
When is written certification for a claim required?
Ans: When a claim exceeds $100,000, contractors must provide the
following written certification (FAR 33.207).
What are protests?
Ans: they provide offerors with a tool to challenge federal contract
award decisions.
Who do you file a protest with?
Ans: The Government Accountability Office
There is a janitorial contract for 2.8 million dollars for the entire base.
What FAR part would you use?
Ans: Could be FAR Part 37 Service Contracting or Far Part 12
Acquisition of Commercial Products and Commercial Services
,What is latent defect?
Ans: is one that is not readily noticeable upon reasonable inspection at
the time of acceptance.
What common form do you use for a modification?
Ans: SF-30
What FAR Part is Acquisition Planning?
Ans: FAR Part 7
What role does the Program Manager plan in Acquistion Planning?
Ans: The PM has overall responsibility of a contract
What is the KO's role in Acquisition Planning?
Ans: Ensures plan is implemented and developed.
What are the two parts of the Pre-award phase?
Ans: Develop Solicitation
, Develop offer
Who develops a solicitation?
Ans: The Government & The Buyer.
Who prepares an offer?
Ans: The Contractor and the seller
During the post-award phase while the contract is being performed, who
has responsibility for quality?
Ans: The Seller
What does the award phase involve?
Ans: Involves all work performed by the buyer and seller
What are the three phases of a life cycle?
Ans: Pre-award Phase
Award Phase
Post-award phase