Which of the following can pose a threat to the sustainability features of a project?
a. Life Cycle Assessment
b. Value engineering
c. Critical path method scheduling
d. Extended warranties
Give this one a try later!
b. Value engineering
, How does ASHRAE define commissioning?
a. A quality-oriented process for achieving, verifying, and documenting that the
performance of facilities, systems, and assemblies meets defined objectives and
criteria
b. A delivery system that seeks to align interests, objectives and practices, even in a
single business
c. The best way to test and balance any heating, ventilation and air conditioning
system
d. The final step in well planned construction process
Give this one a try later!
a. A quality-oriented process for achieving, verifying, and documenting that
the performance of facilities, systems, and assemblies meets defined
objectives and criteria
Which of these is NOT a common feature of a sustainable building project?
a. Wasted energy
b. Energy conservation
c. Renewable energy
d. Water conservation
Give this one a try later!
a. Wasted energy
Choose the correct term to fill in the blank: Resource conservation and occupant
____________ are primary objectives of design, engineering and construction.
a. Satisfaction and education
b. Exposure to sunlight
c. Security
a. Life Cycle Assessment
b. Value engineering
c. Critical path method scheduling
d. Extended warranties
Give this one a try later!
b. Value engineering
, How does ASHRAE define commissioning?
a. A quality-oriented process for achieving, verifying, and documenting that the
performance of facilities, systems, and assemblies meets defined objectives and
criteria
b. A delivery system that seeks to align interests, objectives and practices, even in a
single business
c. The best way to test and balance any heating, ventilation and air conditioning
system
d. The final step in well planned construction process
Give this one a try later!
a. A quality-oriented process for achieving, verifying, and documenting that
the performance of facilities, systems, and assemblies meets defined
objectives and criteria
Which of these is NOT a common feature of a sustainable building project?
a. Wasted energy
b. Energy conservation
c. Renewable energy
d. Water conservation
Give this one a try later!
a. Wasted energy
Choose the correct term to fill in the blank: Resource conservation and occupant
____________ are primary objectives of design, engineering and construction.
a. Satisfaction and education
b. Exposure to sunlight
c. Security