Which of the following should be developed at the outset of the project to establish
the overall schedule completion goals of all the future phases: project budget and
baseline schedule, the PRD, the high level WBS, the low level WBS, the master
schedule, None of the choices
Give this one a try later!
, A master schedule should be developed at the outset of the project to
establish the overall schedule completion goals of all the future phases .
This master schedule has to be subject to the client's review and
acceptance .
CPM canNOT be used to detect inaccuracy in the logic of the plan . True or False
Give this one a try later!
False . CPM can be used to ensure that the logic of the plan is accurate
thus being able to provide measure of importance for each task and create
a graphical display useful for task control .
With the design - build DB method , the building owner contracts with : one single
entity, multiple contractors, an agent
Give this one a try later!
With the design build DB method the building owner contracts with a single
entity to provide both the design and construction of the building . This is
often being referred to as a form of EPC ( engineer , procure , and
construct ) or turnkey construction
Which of the following is the document that sets out how a project is to be managed:
PRD, Charter, Mission Statement, IPD, WBS, PMP, None of the choices
Give this one a try later!
, The Project Management Plan PMP is the document that sets out how the
project is to be managed executed monitored controlled , and closed
throug the phases of its life cycle It may be updated as the project
progresses
_______ Stage is where the building owner selects the contractor and executes the
construction agreement: Stage is where the building owner selects the contractor and
executes the construction agreement: Conceptual, Procurement, Construction, None
of the choices .
Give this one a try later!
Procurement: Stage the building owner selects the contractor and executes
the construction agreement which will eventually progress through to
Construction Stage
Owner - Builder operation is mostly for: very small owner that has a steady flow of
small on - going projects, very large owner that has a steady flow of on - going
projects
Give this one a try later!
Owner Builder operation is mostly for very large owner that has a steady
flow of on going projects so to maintain large enough work force for in
house operation
PERT networks can be used to describe projects mathematically as ( choose all that
apply ) : jobs, headcounts, variable costs, events, lengths of duration, None of the
choices
the overall schedule completion goals of all the future phases: project budget and
baseline schedule, the PRD, the high level WBS, the low level WBS, the master
schedule, None of the choices
Give this one a try later!
, A master schedule should be developed at the outset of the project to
establish the overall schedule completion goals of all the future phases .
This master schedule has to be subject to the client's review and
acceptance .
CPM canNOT be used to detect inaccuracy in the logic of the plan . True or False
Give this one a try later!
False . CPM can be used to ensure that the logic of the plan is accurate
thus being able to provide measure of importance for each task and create
a graphical display useful for task control .
With the design - build DB method , the building owner contracts with : one single
entity, multiple contractors, an agent
Give this one a try later!
With the design build DB method the building owner contracts with a single
entity to provide both the design and construction of the building . This is
often being referred to as a form of EPC ( engineer , procure , and
construct ) or turnkey construction
Which of the following is the document that sets out how a project is to be managed:
PRD, Charter, Mission Statement, IPD, WBS, PMP, None of the choices
Give this one a try later!
, The Project Management Plan PMP is the document that sets out how the
project is to be managed executed monitored controlled , and closed
throug the phases of its life cycle It may be updated as the project
progresses
_______ Stage is where the building owner selects the contractor and executes the
construction agreement: Stage is where the building owner selects the contractor and
executes the construction agreement: Conceptual, Procurement, Construction, None
of the choices .
Give this one a try later!
Procurement: Stage the building owner selects the contractor and executes
the construction agreement which will eventually progress through to
Construction Stage
Owner - Builder operation is mostly for: very small owner that has a steady flow of
small on - going projects, very large owner that has a steady flow of on - going
projects
Give this one a try later!
Owner Builder operation is mostly for very large owner that has a steady
flow of on going projects so to maintain large enough work force for in
house operation
PERT networks can be used to describe projects mathematically as ( choose all that
apply ) : jobs, headcounts, variable costs, events, lengths of duration, None of the
choices