1. Which clause is related to Acquisition? 52.215 - Instructions to Offerors
- Competitive Acquistion
2. What is considered a contract action? Contract action means any oral
or written action that results in
the purchase, rent, or lease of
supplies or equipment, services,
or construction.
3. What is latent defect? is one that is not readily
noticeable upon reasonable
inspection at the time of
acceptance.
4. Who accepts the burden of latent defect? The burden is on the
government to prove that
defective material and
workmanship was the probable
cause of product failure or non-
conformance.
Contractor claims are submitted
5. Who can you submit a claim to?
to the KO
6. What is a claim? a written demand or assertion
by one of the contracting parties
seeking (i) payment of a
specific sum of money, (ii)
adjustment or interpretation of
contract terms, or (iii) other
relief arising under or relating
to the contract.
7. When is written certification for a claim required? When a claim exceeds
$100,000, contractors must
provide the following written
certification (FAR 33.207).
, CON 3990V CERTIFICATION TEST QUESTIONS AND ANSWERS ACTUA
EXAM | LATEST UPDATE 2026/2027 | GUARANTEED PASS | ALREADY
GRADED A+.
8. Who do you file a protest with?
The Government
Accountability Office
9. There is a janitorial contract for
2.8 million Could be FAR Part
37 Service Contracting dollars
for the entire base. What FAR
part or Far Part 12 Acquisition
of Commercial
would you use? Products and Commercial Services
10. What common form do you use
for a modi- SF-30 fication?
11. What FAR Part is Acquisition
Planning? FAR Part 7
12. What role does the Program
Manager plan The PM has
overall responsibility of a conin
Acquistion Planning? tract
, CON 3990V CERTIFICATION TEST QUESTIONS AND ANSWERS ACTUA
EXAM | LATEST UPDATE 2026/2027 | GUARANTEED PASS | ALREADY
GRADED A+.
13. What is the KO's role in
Acquisition Plan- Ensures plan
is implemented and develning?
oped.
14. What are the three phases of a
life cycle? Pre-award Phase
Award Phase
Post-award phase
15. What are the two parts of the
Pre-award Develop
Solicitation phase? Develop
offer
16. Who develops a solicitation?
The Government & The
Buyer.
17. Who prepares an offer? The
Contractor and the seller
18. The Seller
During the post-award phase while the contract is
being performed, who has responsibility for
quality?
19. What does the award phase
involve? Involves all work
performed by the buyer
and seller