SWM DEQ PLAN REVIEWER EXAM QUESTIONS AND ANSWERS VERIFIED 100% CORRECT Name the 5 steps in order of the permitting process - ANSWER -submittal of ESC plans and SWM plans, SWM plan review and approval, registration statement entry into Construction GP, Construction GP approved by DEQ, Locality VSMP authority approval to start land disturbance The locality VSMP authority has ___ days to determine the completeness of a stormwater management plan and to notify the applicant of its determination - ANSWER -15 If the plan is complete and the applicant has been notified within 15 days of submission, the locality VSMP authority (plan reviewer) has ___ days from the time of notification to review the plan - ANSWER -60 Operators of a single-family detached residential structures that disturb equal to or greater than one acre of land are - ANSWER -not required to submit a registration statement VSMP authority must keep project records, including approved SWM plans and registration statements, for ___ years after state permit termination or project completion - ANSWER -3 years VSMP authority must keep post construction stormwater management facility inspection records for __ years from the date of inspection - ANSWER -5 DEQ is required to conduct a program review once every - ANSWER -5 years A locality VSMP must be at least as stringent as what state permit? - ANSWER Construction GP What plans must a locality's ordinance require to be submitted and approved? - ANSWER -ESC plan, SWM plan The Construction GP includes ___ different inspection frequencies - ANSWER -2 SWPPP inspection schedule if discharging to impaired waters - ANSWER -at least once every 4 business days or at least once every 5 business days and no later than 24 hours following a measurable storm event SWPPP inspection schedule for standard inspections - ANSWER -at least once every 5 business days, at least once every 10 business days and no later than 24 hours following a measurable storm event For all sites where areas have been temporarily stabilized or LDA have been suspended due to frozen conditions, inspections can be done - ANSWER -once a month Representative inspections may not be used when - ANSWER -utility line installation, pipeline construction, or other similar linear construction activities SWPPP inspection schedule discharge into impaired waters, surface waters with an applicable TMDL or exceptional waters The qualified personnel's SWPPP inspection report must included with the SWPPP no later than - ANSWER -4 days following inspection Corrective actions made based on inspections must be done - ANSWER -as soon as practicable but no later than seven days, or a longer period of time as approved by the VSMP Changes in the SWPPP must be made in a __ day period - ANSWER -7 For reports of unauthorized discharges, must notify DEQ upon discovery within a ___ window and a written report should be submitted within ___ of discovery of discharge - ANSWER -24 hours, 5 days Concrete Wash Water must be directed into a - ANSWER -leak-proof container or leak-proof settling basin Is the P2 plan approved by the VSMP authority? - ANSWER -No Are support activities covered under the Construction GP? - ANSWER -Yes, if it meets specific criteria If a Construction GP covers support activities do you have to inspect it? - ANSWER -Yes How long must a VSMP authority keep inspection reports? - ANSWER -3 years What are the three requirements for concrete wash water? - ANSWER -Must be removed properly, must not overflow, put in a leak-proof basin Stormwater BMPS use three primary mechanisms to control pollution - ANSWER -infiltration, settling, vegetative uptake or filtering Top three misused materials in BMPs - ANSWER -geotextile fabric, stones, soil media What is a measurable storm event? - ANSWER -0.25 in/24 hour period The operator must submit the DEQ Notice of Termination form to the VSMP authority - ANSWER -within 30 days of meeting one or more of the following conditions When is permanent vegetation considered established? - ANSWER -uniform, mature enough to survive, will inhibit erosion Record drawings must be sealed and signed by a - ANSWER -professional registered in VA Within ___ days of completing the requirements of the permit conditions, the locality VSMP authority must return or terminate any bonds or securities provided by the operator - ANSWER -60

Show more Read less
Institution
SWM DEQ PLAN
Course
SWM DEQ PLAN









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
SWM DEQ PLAN
Course
SWM DEQ PLAN

Document information

Uploaded on
December 11, 2025
Number of pages
11
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

SWM DEQ PLAN REVIEWER EXAM QUESTIONS
AND ANSWERS VERIFIED 100% CORRECT
Name the 5 steps in order of the permitting process - ANSWER -submittal of ESC
plans and SWM plans, SWM plan review and approval, registration statement
entry into Construction GP, Construction GP approved by DEQ, Locality VSMP
authority approval to start land disturbance

The locality VSMP authority has ___ days to determine the completeness of a
stormwater management plan and to notify the applicant of its determination -
ANSWER -15

If the plan is complete and the applicant has been notified within 15 days of
submission, the locality VSMP authority (plan reviewer) has ___ days from the
time of notification to review the plan - ANSWER -60

Operators of a single-family detached residential structures that disturb equal to or
greater than one acre of land are - ANSWER -not required to submit a registration
statement

VSMP authority must keep project records, including approved SWM plans and
registration statements, for ___ years after state permit termination or project
completion - ANSWER -3 years

VSMP authority must keep post construction stormwater management facility
inspection records for __ years from the date of inspection - ANSWER -5

DEQ is required to conduct a program review once every - ANSWER -5 years

A locality VSMP must be at least as stringent as what state permit? - ANSWER -
Construction GP

What plans must a locality's ordinance require to be submitted and approved? -
ANSWER -ESC plan, SWM plan

, The Construction GP includes ___ different inspection frequencies - ANSWER -2

SWPPP inspection schedule if discharging to impaired waters - ANSWER -at least
once every 4 business days or at least once every 5 business days and no later than
24 hours following a measurable storm event

SWPPP inspection schedule for standard inspections - ANSWER -at least once
every 5 business days, at least once every 10 business days and no later than 24
hours following a measurable storm event

For all sites where areas have been temporarily stabilized or LDA have been
suspended due to frozen conditions, inspections can be done - ANSWER -once a
month

Representative inspections may not be used when - ANSWER -utility line
installation, pipeline construction, or other similar linear construction activities
SWPPP inspection schedule discharge into impaired waters, surface waters with an
applicable TMDL or exceptional waters

The qualified personnel's SWPPP inspection report must included with the
SWPPP no later than - ANSWER -4 days following inspection

Corrective actions made based on inspections must be done - ANSWER -as soon
as practicable but no later than seven days, or a longer period of time as approved
by the VSMP

Changes in the SWPPP must be made in a __ day period - ANSWER -7

For reports of unauthorized discharges, must notify DEQ upon discovery within a
___ window and a written report should be submitted within ___ of discovery of
discharge - ANSWER -24 hours, 5 days

Concrete Wash Water must be directed into a - ANSWER -leak-proof container or
leak-proof settling basin
$11.99
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
TopGradeGuru
1.5
(2)

Get to know the seller

Seller avatar
TopGradeGuru Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
10
Member since
1 year
Number of followers
0
Documents
2429
Last sold
1 month ago
GRADEHUB

We provide access to a wide range of professionally curated exams for students and educators. It offers high-quality, up-to-date assessment materials tailored to various subjects and academic levels. With instant downloads and affordable pricing, it's the go-to resource for exam preparation and academic success.

1.5

2 reviews

5
0
4
0
3
0
2
1
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions