CLC -222 Contracting Officer's
Representatives Questions with Answers
(100% Correct Answers)
Which of the following are activities associated with monitoring
performance?(Select all that apply.) Answer: Ensuring safety and compliance,
conducting inspections, acceptance and payment, and overseeing government
property are activities associated with monitoring performance.
The contractor has primary responsibility for ensuring the quality and
timeliness of their supplies or services in meeting contract performance
standards. Answer: True. The contractor has primary responsibility for
ensuring the quality and timeliness of their supplies or services in meeting
contract performance standards.
Which of the following is NOT part of a contract management plan? Answer:
How the COR will manage contractor personnel is NOT part of a contract
management plan.
The Post Award Orientation helps to ensure the government and contractor are
"on the same page" from the start of the contract. Answer: The Post Award
Orientation helps to ensure the government and contractor are "on the same
page" from the start of the contract.
Which of the following are assessment factors used in measuring performance?
(Select all that apply.) Answer: Cost control, quality, timeliness, customer
satisfaction, and management of key personnel are all assessment factors used
in measuring performance.
What should a COR should do if he/she witnesses the circumstances seen in
this image? Answer: A COR should direct the contractor to stop (to protect life,
limb, eyesight or destruction to property), document it and notify the KO if
he/she witnesses the circumstances seen in the image shown.