The purpose of Construction Quality Management is to: - Answer- Achieve the quality
established by properly developed requirements through the combined responsibility,
but separate, efforts of contractor and Government personnel
Construction Quality Management is the performance of tasks, which ensure that
design and construction is performed: - Answer- According to plans and specifications,
on time, within a defined budget and a safe work environment.
Partnering relationships are based upon: - Answer- Building trust and dedication to
common goals
It is the responsibility of Quality Assurance Personnel to: - Answer- Periodically verify
that the contractors system of control is working effectively.
An effective contractor quality control (CQC) program will: - Answer- Be an incentive for
work to be done correctly the first time resulting in earlier completion, reduced field
overhead costs, and greater profits.
The success or failure of all contractors is based upon: - Answer- The ability to control
costs, finance work, estimate jobs, schedule the work, and maintain effective quality
control.
Quality Assurance Personnel have the responsibility to: - Answer- Require contractors
to maintain the quality specified in the plans and specifications.
Inspection is: - Answer- The process by which ongoing and completed work is
examined
During the punch-out inspection of a project: - Answer- Quality Assurance Personnel
must assure that the contractor prepares a punch-list and makes corrections.
If there is disagreement whether the contractor's work complies with the contract: -
Answer- The government makes the final determination
Characteristics that describe a definable feature of work (DFOW) include: - Answer-
Cross-referenced listings to the contractors construction schedule that may have more
than one definable feature under a section of the specifications.
The _____________________ consists of daily checks of the work to assure continuing
compliance with contract requirements. - Answer- Follow-up phase
The Quality Assurance Plan: - Answer- Is a government management tool establishing
staffing, training, pre-award activities, and surveillance activities.