SIMMONS/ODE, ELECTRICAL WIRING COMMERCIAL, 18E © 2024, 9780357767115;
ST
CHAPTER 1: COMMERCIAL BUILDING PLANS AND SPECIFICATIONS
SUT
TABLE OF CONTENTS
Review ..........................................................................................................................................................
UV
1
VIAI
Note to instructor: It is recommended that students be required to respond, where appropriate, with
answers that are complete sentences.
A__A
REVIEW
APP
Refer to the National Electrical Code or the working drawings when necessary. Where
applicable, responses should be written in complete sentences.
PPR
1. What section of a commercial building’s specification contains a list of contract
documents?
RO
Answer: A list of the contract documents is contained in General Clauses and Conditions. A
listing of the Commercial Building contract documents is presented in this chapter under the
heading “Commercial Building Plans.” The instructor may wish to have the students check over
this listing and compare it with the plans provided.
VEE
2. The requirement for temporary light and power at the job site will be found in what
portion of a commercial building’s specification?
DD?
Answer: The Supplementary General Conditions specifies the job site requirements for
temporary light and power. In some contracts, this electrical system becomes the responsibility of
the general contractor; in other contracts, it is the electrical contractor’s responsibility to install
???
and maintain the temporary electrical system. The instructor may wish to refer the student to
NEC Article 590 and discuss the requirements in detail.
?
,ST
3. The electrician uses the Schedule of Working Drawings for what purpose?
Answer: The electrician uses the Schedule of Working Drawings to determine whether all of the
SUT
drawings are at hand. The information on “the other sheets” may be very important, especially in
coordinating with other contractors.
4. Complete the following items by indicating the letter(s) designating the correct source(s)
UV
of information:
No. Answer Item Information
VIAI
4. Sections Ceiling height Sections, Sheet A6
A__A
5. Electrical Electrical receptacle Electrical symbol schedule, Chapter symbol style
2, Figure 2–6 schedule
6. Electrical Electrical outlet Electrical layout drawings, Sheets
APP
layout location El, E2, and E3 drawings
7. Elevations Exterior wall finishes Elevations, Sheets A4 and A5
PPR
8. Site plan Grading elevations Site plan, Sheet A4
RO
9. Electrical Panelboard schedules Electrical layout drawings, Sheet E4 layout
drawings
10. Architectural Room width Architectural floor plan, Sheets Al, floor plan A2,
VEE
and A3
11. Architectural Swing of door Architectural floor plan, Sheets Al, floor plan A2,
DD?
and A3
12. Sections View of interior wall Sections, Sheet A6
???
Match the items on the left with those on the right by writing the letter designation of
the appropriate organization from the list on the right.
?
, 13. NEC Electrical Code National Electrical Code (NEC)
14. IAEI Electrical inspectors International Association of
ST
Electrical Inspectors (IAEI)
SUT
15. NFPA Fire codes National Fire Protection Association
(NFPA)
UV
16. IESNA Lighting information Illuminating Engineering
Society of North America
VIAI
(IESNA)
17. UL Listing service Underwriters Laboratories, Inc.
A__A
(UL)
18. NEMA Manufacturers’ National Electrical standards Manufacturers
APP
Association
(NEMA)
19. PE Seal Professional Engineer (PE)
PPR
RO
Match the items on the left with those on the right by writing the letter
designation of the proper level of NEC interpretation from the list on the right.
20. with Allowed by the Code Shall be permitted, or Shall not special be required,
VEE
NEC permission
21. with May be done Shall be permitted, or Shall not
DD?
special be required, NEC permission
22. shall Must be done Shall, National Electrical Code
???
23. shall Required by the Code Shall, National Electrical Code
24. never Up to the electrician Shall be permitted, or Shall not be required, NEC
?