Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 1 out of 4 pages
Exam (elaborations)

Virginia Exam Advanced questions and 100% correct answers 2025

Document preview thumbnail
Preview 1 out of 4 pages

In the previous year, a company had revenues of $500,000, project overhead of $40,000 and company overhead of $75,000. The company expects the percentage for project and company overhead to remain the same for the current year. The company desires to make a 10% profit on a project it is bidding. The project would have $80,000 in direct costs. What should the bid price be? - correct answer Between $110,000 and $120,000. What is the name of the process when a facilitator meets with the major participants in a project, prior to the commencement of the project, to identify the shared goals of all participants? - correct answer Partnering. A cost plus contract calls for the contractor to receive direct costs for labor and materials, and a markup of 20% of direct costs. The contractor is also to receive a bonus of 15% of savings if total cost to the owner is less than $80,000, and a bonus of $1,000 per day if the project is completed early. Final costs for direct labor and materials are $60,000. The project is completed 3 days early. What is the total amount due the contractor? - correct answer Between $75,001 and $80,000. The owner requests for changes which will cost the contractor $15,000 in labor and materials and $2,250 in overhead costs. With the change, the contractor would be relieved of $18,000 in labor and materials costs, and $2,400 in overhead costs from the original contract. The original bid included profit of 20% of all costs. The contractor wants to make a profit of 20% of all costs on the changes. The adjusted contract price for the change order should be - correct answer a decrease of $3,780. A lump sum contract on a project has a total contract price of $160,000. Retainage has been held back at 10%. The contractor has received progress payments for 75% of the project. The contractor submits a request for final payment for the now completed project. The final payment amount should be for - correct answer more than $50,000. A permit is obtained on Friday, May 1. The materials are to be delivered May 8. The materials are needed when labor begins on May 11. It is estimated that 15 days of labor are REQUIRED. The crew will work every day, including weekends and holidays. The project is scheduled to be completed on June 8. How many float days are available for the labor for this project? - correct answer 13 Which of the following would typically be covered by a contractor's comprehensive general liability insurance policy? - correct answer Damage to adjoining property from a crane accident. A contractor puts in a claim under a comprehensive standard general liability policy. The policy has no additional coverage, riders, or floaters, and has a $500 deductible per occurrence. The claim is for a job-site accident that caused $2,000 of injuries to employees, $1,800 of injuries to a pedestrian,

Content preview

Virginia Exam Advanced
In the previous year, a company had revenues of $500,000, project overhead of $40,000 and
company overhead of $75,000. The company expects the percentage for project and company
overhead to remain the same for the current year. The company desires to make a 10% profit on a
project it is bidding. The project would have $80,000 in direct costs. What should the bid price be? -
✔✔ correct answer Between $110,000 and $120,000.



What is the name of the process when a facilitator meets with the major participants in a project,
prior to the commencement of the project, to identify the shared goals of all participants? - ✔✔
correct answer Partnering.



A cost plus contract calls for the contractor to receive direct costs for labor and materials, and a
markup of 20% of direct costs. The contractor is also to receive a bonus of 15% of savings if total cost
to the owner is less than $80,000, and a bonus of $1,000 per day if the project is completed early.
Final costs for direct labor and materials are $60,000. The project is completed 3 days early. What is
the total amount due the contractor? - ✔✔ correct answer Between $75,001 and $80,000.



The owner requests for changes which will cost the contractor $15,000 in labor and materials and
$2,250 in overhead costs. With the change, the contractor would be relieved of $18,000 in labor and
materials costs, and $2,400 in overhead costs from the original contract. The original bid included
profit of 20% of all costs. The contractor wants to make a profit of 20% of all costs on the changes.
The adjusted contract price for the change order should be - ✔✔ correct answer a decrease of
$3,780.



A lump sum contract on a project has a total contract price of $160,000. Retainage has been held
back at 10%. The contractor has received progress payments for 75% of the project. The contractor
submits a request for final payment for the now completed project. The final payment amount
should be for - ✔✔ correct answer more than $50,000.



A permit is obtained on Friday, May 1. The materials are to be delivered May 8. The materials are
needed when labor begins on May 11. It is estimated that 15 days of labor are REQUIRED. The crew
will work every day, including weekends and holidays. The project is scheduled to be completed on
June 8. How many float days are available for the labor for this project? - ✔✔ correct answer 13



Which of the following would typically be covered by a contractor's comprehensive general liability
insurance policy? - ✔✔ correct answer Damage to adjoining property from a crane accident.



A contractor puts in a claim under a comprehensive standard general liability policy. The policy has
no additional coverage, riders, or floaters, and has a $500 deductible per occurrence. The claim is for
a job-site accident that caused $2,000 of injuries to employees, $1,800 of injuries to a pedestrian,

Document information

Uploaded on
November 4, 2025
Number of pages
4
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers
$19.49

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
brittton
3.4
(20)
Sold
156
Followers
95
Items
5174
Last sold
1 month ago


Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions