performance-based code A _________ outlines a requirement that a design has to meet
but does not state that a particular method or material must be used to meet the
requirements.
False True or False
A performance-based code/standard gives the designer less freedom than a prescriptive-based
code/standard.
code A ____________ is a collection of rules and regulations that has been enacted by
law in a particular jurisdiction.
All of the answers are correct An exception to a code may occur in which of the following
forms?
A. Variances
B. Appeals
C. Modifications
D. All of the answers are correct
True True or False:
Fire and life safety inspectors acting alone have little authority to approve requests for
modification of code requirements.
,False True or False:
Falls are the leading cause of unintentional injury deaths for adults over the age of 65.
All of the answers are correct Model code organizations include:
A. National Fire Protection Association (NFPA)
B. International Code Council (ICC)
C. American Society of Mechanical Engineers (ASME)
D. all answers are correct
All of the answers are correct The Iroquois Theater fire resulted in which of the following
changes for other theater buildings:
A. Outward open exit doors must remain unlocked
B. Exit doors fitted with panic hardware
C. Flame-resistant scenery, props, and curtains
D. all answers are correct
C. Cocoanut Grove Fire Many jurisdictions did not include restaurants and nightclubs in
the code classification of public places until which historic fire:
A. Beverly Hill Supper Club Fire
B. The Station Nightclub Fire
C. Cocoanut Grove Fire
D. Our Lady of the Angles School Fire
, All of the answers are correct Sanctions issued by a jurisdiction may be in the form of
__________.
A. Stop Work Orders
B. Fines
C. Court summonses
D. all answers are correct
All of the answers are correct Which of the following technological tools may be used to
schedule, record, and file inspection documents?
A. smart phone
B. tablet
C. laptop
D. all answers are correct
True True or False:
The plan review process can be broken down into the following phases: Application, Review,
Approval, Site Visits, and Commissioning.
C. design professional's It is the ______________ responsibility to determine the
occupancy classification for the proposed building and identify the intended use of each room
or section of the building.
A fire marshal's