After driving a sheet pile B) By drilling a hole through the pile into the soil, inserting
into firm soil, what is the a steel cable into the hole, grouting the hole, and
tightening the cable after the grout dries.
best mechanism to secure
the sheet pile with the
firm soil to keep it in
position as the excavation
progresses? Assume the
excavation area is wide
and no obstructions are
allowed in the area.
A) By tying the pile with
the firm soil using a screw
anchor
B) By drilling a hole
through the pile into the
soil, inserting a steel
cable into the
hole, grouting the hole,
and tightening the cable
after the grout dries.
C) By using wales and
bracings.
D) By using cross-lot
bracings.
What portion of a building Superstructure
structure is responsible for
directly supporting to in-
service load of the
,building?
One of the following C) Differential settlement of foundations poses safety and
statements is true about serviceability damages.
foundation settlement
A) Uniform foundation
settlement does no
seriously affect the
building.
B) Foundation settlement
can completely prevented
by comparative loose
soil.
C) Differential settlement of
foundations poses safety
and serviceability
damages.
D) Uniform foundations
settlement affects the
safety of a building more
than it does to its
serviceability.
What type of shallow Matt Foundation
foundation is the best
choice for a two - story
concrete
residential building to be
constructed on weak soil?
One of the following is not E) None
an example of a deep
foundation
A) Caisson
B) Pier
C) Driven Pile
D) Bored Pile
E) None
,What is the construction Compacted sub grade, formwork, compacted gravel, moisture
process when protector, insulator,
constructing a slab-on-grade? reinforcing bars, utility lines, concrete work
One of the following is not D) Ensuring that the construction work is completed on time.
related to site remediation.
A) Placing productive soil on
the site after the
construction activity is
completed.
B) Restoring natural habitats on
the site.
C) Ensuring that the site
environment is safe and
sound.
D) Ensuring that the
construction work is
completed on time.
, Identify the statement that C) The removal of roots, buried water tanks and utility lines from
does not belong to the site.
earthwork in construction
activities.
A) The removal of top
soil from the
construction site.
B) Increasing the bearing
strength of the natural
ground.
C) The removal of roots,
buried water tanks and
utility lines from the site.
D) spreading and compacting
selected soil.
The purpose of grading of D) All are possible answers.
construction site is ______
A) To get a leveled site area.
B) To pave a well-graded road.
C) To construct ditches and
waterways to drain water
from the construction
site.
D) All are possible answers.
One of the following is not C) The excavation depth for the foundations of all residential
true about excavation for buildings is the same.
foundations.
A) The depth of the
excavation should at least
be below the frost line.
B) The excavation should
reach the soil with the
required bearing strength.
C) The excavation depth for the
foundations of all
residential buildings is the