Summary

Summary: Supply Chain Design & Planning

Rating
-
Sold
1
Pages
28
Uploaded on
15-10-2025
Written in
2025/2026

This is a summary of the course Supply Chain Design & Planning, which is a part of the Masters program: Supply Chain Management This summary consists of: - all lectures - all required chapters of the textbook

Institution
Course










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Study
Course

Document information

Uploaded on
October 15, 2025
Number of pages
28
Written in
2025/2026
Type
Summary

Subjects

Content preview

Lecture 2 – Inventory Management, Risk Pooling, and Distribution

Why do you need inventory?
▪ Uncertainty in customer demand
▪ Uncertainty in supplies
▪ Delivery lead times
▪ Incentives for larger shipments


Economic order quantity: Q ¿ =
√ 2 KD
h
K = fixed cost every time an order is placed
h = holding cost per unit held

Demand uncertainty:
▪ The forecast is always wrong
▪ The longer the forecast horizon, the worse the forecast
▪ Aggregate forecasts are more accurate

Single period models: one ordering opportunity only before demand occurs

Continuous demand, Normal distribution
-> Q=μ+ z∗σ

Optimal service level = Marginal profit / (Marginal profit + Marginal cost)

(Q,R) policy = whenever inventory level falls to a reorder level ‘R’, place an
order for ‘Q’ units R=L∗AVG+ z∗STD∗√ L

R=AVG∗AVGL+ z √ AVGL∗STD 2∗AVG 2∗STDL2Q=
opportunities:
√ 2 K∗AVG Multiple order
h

1. Short intervals
-> during each inventory review, if the inventory position falls below ‘s’, order
enough to raise the inventory position to ‘S’
2. Longer intervals
-> always order after an inventory level review to fill the inventory to a pre-
determined target inventory level (the base-stock level)

Forms of risk-pooling:
1. Location pooling
= keep inventory at a central location to satisfy demand in multiple markets,
demand variability will be reduced
2. Standardized design (product pooling)
-> product category demand is easier to predict
3. Delayed differentiation
= delay of product differentiation until closer to the sale of the product
4. Production flexibility (capacity pooling)
= product multiple products/models in one factory

The newsvendor problem: “how many newspapers to buy in the morning to
maximize profits?”

,Surplus cost (overage cost): Co = purchase cost – salvage value
Shortage cost (underage cost): Cu = sales price – purchase cost

Critical ratio: CR = Cu / (Co + Cu)
F(Q*) = CR
-> F is the cdf of demand




Lecture 4 : Supply Contracts & The Value of Information

Optimal Service Level (CSL*) = CU / (CU + CO)

Make To Order contracts (MTO):
1. Buy-Back Contract

, = supplier agrees to buy back leftover inventory for a predetermined price
▪ Requires suppliers to have an effective reverse logistics system and may
increase logistics cost
▪ Buyers have an incentive to push the product not under the buyback contract
2. Wholesale Price Contract
= buyer shares some of its revenue with the supplier in return for a discount on
the wholesale price
▪ Requires suppliers to monitor the buyer’s revenue and thus increases
administrative cost
▪ Buyers have an incentive to push competing products with higher profit
margins
-> both contracts will increase total profits shared by the two parties
3. Quantity-Flexibility Contract
= supplier provides a full refund for returned items as long as the number of
returns is no larger than a certain quantity
4. Sales Rebate Contract
= a rebate is paid by the supplier for any item sold above a certain quantity

Make To Stock contracts (MTS):
1. Pay-Back Contract
= the buyer agrees to pay some agreed-upon price for the inventory produced by
the supplier but not purchased
▪ Buyer’s risk increases
▪ supplier has an incentive to produce more units
2. Cost-Sharing Contract
= the buyer shares some of the production cost with the supplier, in return for a
discount on the wholesale price
▪ Reduces effective production cost for the supplier
▪ Supplier has an incentive to produce more units

Contracts with Asymmetric Information:
1. Capacity Reservation Contract
= buyer pays to reserve a certain level of capacity at the supplier
▪ A menu of prices for different capacity reservations provided by supplier
▪ Buyer signals true forecast by reserving a specific capacity level
2. Advance Purchase Contract
= supplier charges special price before building capacity
▪ When demand is realized, price charged is different
▪ Buyer’s commitment to paying the special price reveals the buyer’s true
forecast

Operational Causes for the Bullwhip effect:
1. Demand forecasting
-> estimates about demand are regularly modified
2. Lead time
-> small changes in demand estimates are magnified
3. Batch ordering
-> a large order followed by several periods of no order
4. Price fluctuations
-> discounts or promotions cause forward buying

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
joesvanderstok Tilburg University
Follow You need to be logged in order to follow users or courses
Sold
136
Member since
2 year
Number of followers
37
Documents
32
Last sold
4 days ago

4.1

10 reviews

5
3
4
5
3
2
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions