CMP 101 Exam 2 2026 Questions and
Answers
CM is the - Correct answer-planning
scheduling
evaluation
and controlling
of construction tasks and activities to accomplish specific objectives as provided
for in the contract documents
Design-Build - Correct answer-Single Entity Designs and Builds the structure
Single Contract for the owner
Fast tracking, much efficiency
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
, Referred to as "single source" project delivery.
Only one contract exists. It is between the owner and design-build team.
Design-build entity responsible for both the design and construction of the project.
Design-Bid-Build - Correct answer-One contract to designer, one to constructor
Design(Architect) the project by producing the plans and specifications, then
Send plans and specifications out for bid(GC or Builder) and accept the lowest
qualified bid, then
Build(GC or Builder) the project.
Construction Management At Risk (CMAR) - Correct answer-Acts as a consultant
to the owner during design and development phases. Essentially acts as general
contractor (GC) during the construction phase, who will deliver the project at a
guaranteed maximum price (GMP).
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2
Answers
CM is the - Correct answer-planning
scheduling
evaluation
and controlling
of construction tasks and activities to accomplish specific objectives as provided
for in the contract documents
Design-Build - Correct answer-Single Entity Designs and Builds the structure
Single Contract for the owner
Fast tracking, much efficiency
©COPYRIGHT 2025, ALL RIGHTS RESERVED 1
, Referred to as "single source" project delivery.
Only one contract exists. It is between the owner and design-build team.
Design-build entity responsible for both the design and construction of the project.
Design-Bid-Build - Correct answer-One contract to designer, one to constructor
Design(Architect) the project by producing the plans and specifications, then
Send plans and specifications out for bid(GC or Builder) and accept the lowest
qualified bid, then
Build(GC or Builder) the project.
Construction Management At Risk (CMAR) - Correct answer-Acts as a consultant
to the owner during design and development phases. Essentially acts as general
contractor (GC) during the construction phase, who will deliver the project at a
guaranteed maximum price (GMP).
©COPYRIGHT 2025, ALL RIGHTS RESERVED 2