ARMY EXPLOSIVES SAFETY SITE PLANNING
CERTIFICATION EXAM NEWEST 2025/2026 NEWEST
ACTUAL EXAM WITH COMPLETE QUESTIONS AND
VERIFIED ANSWERS |ALREADY GRADED A+|
Which three mistakes commonly occur when submitting an
ESSP? - ANSWER-submitting a map without an indication of true
north
Leaving out the lightning protection system (LPS) drawings
Sending a map with no scale indicated
The purpose of an ESSP is to ensure safety, provide
specifications, and - ANSWER-establish limits
ILD is the minimum distance permitted between - ANSWER-two
operating buildings
, Page |2
Your installations is refurbishing an existing PES facility. Do you
need to complete an ESSP? - ANSWER-Yes, and it requires
DDESB approval.
You must submit an ESSP for DDESB approval if the installation
is - ANSWER-Building an ES within an existing ESQD arc
Who must accept identified risks? - ANSWER-Installation
Commander
Failing to submit a successful ESSP can result in impaired
operational capability, decreased production, and - ANSWER-
delay in construction
Which part of the ESSP package contains background
information, site location, and the reason for ESSP submission? -
ANSWER-ESSP narrative
All of these are requirements of an ESSP except? - ANSWER-
Tenant unit approval