A technical evaluation has been completed on a contractor's proposal. The evaluation indicates
the proposal meets technical requirements. What is the lowest color evaluation rating the
technical proposal can receive? - Answer Green
You are the contracting officer on the Wingless Aviation program for the Air Force. The source
selection authority has appointed functional experts to the Source Selection Evaluation Board
(SSEB). Who is responsible for managing the acquisition program including developing and
implementing the acquisition strategy? - Answer Program Manager
When performance-based payments (PBPs) were first introduced, a number of potential
advantages were cited. Of those expected advantages of PBPs, which one of the following has
proven to be an actual advantage? - Answer Improved cash flow for contractor resulting in
win-win for both government and contractor
After reviewing a pre-award survey on a small business, you determine that they are a non-
responsible contractor for this award. Yet, the Small Business Administration (SBA) has issued
them a Certificate of Competency (COC) for this award. What should you do? - Answer Award
the contract to the small business contractor
The selection of good payment events is critical to the performance-based payment process.
Which of the following statements represents a common characteristic of good performance-
based payment events? - Answer They are clear milestones in the path toward ultimate
completion of contract.
You are asked to determine if one of several contractors submitting offers on a solicitation is
responsible. The requirement is for critically needed parts and has a short turn-around time
from award to delivery. Based on data you obtain, you notice that this contractor is operating
three fully manned shifts a day and has several months of backlogged work still waiting to start.
Under which General Standard of Responsibility might you determine the contractor to be non-
responsible? - Answer Not able to comply with the required or proposed delivery or
performance schedule
You are about to issue a fixed-price contract for a mature, stable production program that will
include contract financing. Which type of financing should you consider first? - Answer