100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.6 TrustPilot
logo-home
Exam (elaborations)

DBIA EXAM 3 NEWEST VERSION 2026 ACTUAL EXAM COMPLETE 140 QUESTIONS AND CORRECT DETAILED ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+ | WITH A STUDY GUIDE

Rating
-
Sold
-
Pages
41
Grade
A+
Uploaded on
01-10-2025
Written in
2025/2026

Prepare for success on the DBIA Exam 3 with this updated study resource featuring 120 practice questions and detailed answers. Designed to mirror exam-style scenarios, this guide covers design-build fundamentals, procurement, contracts, risk allocation, ethics, project management, and professional practices. Each question includes the correct answer and rationale to support deeper understanding and exam readiness. Updated for 2024–2025, this complete study guide provides the essential tools for students and professionals preparing for the Design-Build Institute of America (DBIA) certification. Build confidence, strengthen knowledge, and achieve exam success with these fully explained practice questions.

Show more Read less
Institution
Course











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Course

Document information

Uploaded on
October 1, 2025
Number of pages
41
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

1 | Page




DBIA EXAM 3 NEWEST VERSION 2026 ACTUAL EXAM
COMPLETE 140 QUESTIONS AND CORRECT DETAILED
ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+ |
WITH A STUDY GUIDE


1.
Design-build delivery is often selected to improve schedule
performance and single-point responsibility.
Which of the following best describes the primary contractual
advantage of design-build?
A) Owner retains separate contracts for design and construction
B) It reduces the owner’s single point of contact for project issues
C) It places design and construction liability with one entity
D) It always lowers project cost compared to other methods
Answer: C — Design-build consolidates responsibility for both
design and construction with one contract entity, simplifying
liability and coordination.




2.
In a progressive design-build procurement, the owner typically:
A) Awards a lump-sum turnkey contract based on 100% design
documents
B) Selects a design-builder early and negotiates the final price as
design progresses
C) Separately bids the design and construction packages
D) Uses a low-bid only selection criterion
Answer: B — Progressive design-build selects a team early and
negotiates GMP/price as design advances, promoting
collaboration.

,2 | Page




3.
Which commercial contract clause most directly allocates delay
risk to the contractor?
A) Force majeure clause
B) Liquidated damages for late completion
C) Payment terms clause
D) Warranty clause
Answer: B — Liquidated damages impose a pre-agreed cost for
late completion, assigning delay risk to the contractor.


4.
An owner wants to encourage innovation while maintaining fair
competition in qualifications-based selection.
Which procurement approach best balances those goals?
A) Lowest responsive bid after full design
B) Qualifications-based selection with a negotiated fee and
performance incentives
C) Single-source award without competition
D) Sealed bid lump sum without prequalification
Answer: B — QBS with negotiated fee and incentives rewards
innovation and selects on qualifications rather than only price.


5.
During early teaming, what is the most important document to
define governance, roles, IP, and confidentiality between potential
partners?
A) Final design contract
B) Teaming agreement (or non-binding teaming letter)
C) Owner’s RFP
D) Building permit application

,3 | Page


Answer: B — A teaming agreement clarifies roles, IP,
confidentiality, and responsibilities during proposal development.


6.
Which risk is typically least transferable to a design-builder in a
standard design-build agreement?
A) Risk of means/methods used by the contractor
B) Risk of design errors created by the design-builder
C) Risk of changes in law that affect project requirements
D) Risk of contractor’s performance default
Answer: C — Risks arising from changes in law are often retained
by the owner or negotiated as exceptions; they are harder to fully
transfer.


7.
A design-builder discovers a subsurface condition materially
different from the contract’s geotechnical report. Best first step:
A) Proceed as if nothing changed and absorb costs
B) Immediately stop work and await written direction from the
owner/CM
C) Document the condition, notify the owner per contract notice
requirements, and propose options
D) Continue and file a claim after project completion
Answer: C — Timely documentation and prompt notice per
contract are essential to preserve entitlement and propose
corrective options.


8.
Which incentive structure aligns contractor behavior with owner
schedule goals most directly?

, 4 | Page


A) Cost-plus fee without incentives
B) Lump-sum fixed price only
C) GMP with schedule-based bonuses and liquidated damages
D) Time and materials billing
Answer: C — Combining GMP with schedule bonuses and
liquidated damages creates both carrot and stick alignment for
schedule performance.


9.
Under a single-point design-build contract, who typically holds
professional liability for design defects?
A) Owner only
B) Design subcontractor only
C) The design-builder (as the contracted entity), with possible
flow-down to design consultants
D) Construction subcontractor only
Answer: C — The design-builder assumes professional liability to
the owner, often flowing obligations to design subconsultants.


10.
Which best practice improves cost certainty in the DB
procurement phase?
A) Avoiding any third-party reviews
B) Using independent cost estimating and validating risk
contingencies before price agreement
C) Relying solely on contractor’s unverified pricing
D) Eliminating design milestones from the procurement timeline
Answer: B — Independent estimates and validated risk
contingencies increase cost transparency and certainty.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
HealthStudyPro Johns Hopkins School Of Public Health
Follow You need to be logged in order to follow users or courses
Sold
110
Member since
8 months
Number of followers
16
Documents
1406
Last sold
4 hours ago
HealthStudyPro

Welcome to HealthStudyPro – Your 24/7 Partner for Nursing & Healthcare Exam Success! At HealthStudyPro, we provide premium, A+ rated study materials to help nursing and healthcare students excel in their exams. Whether you're preparing for the HESI RN Exit Exam, ATI, NCLEX, or other critical assessments, we’ve got you covered with accurate, up-to-date, and verified resources.

4.2

34 reviews

5
20
4
4
3
8
2
1
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions