Which four items are required parts of the Transmittal
Memorandum? - ANSWER-Applicable explosives safety
references
Site location
Requested approve by date
Point of contact (POC) for the ESSP
Which three mistakes commonly occur when submitting an
ESSP? - ANSWER-submitting a map without an indication of true
north
Leaving out the lightning protection system (LPS) drawings
, Page |2
Sending a map with no scale indicated
The purpose of an ESSP is to ensure safety, provide
specifications, and - ANSWER-establish limits
ILD is the minimum distance permitted between - ANSWER-two
operating buildings
Your installations is refurbishing an existing PES facility. Do you
need to complete an ESSP? - ANSWER-Yes, and it requires
DDESB approval.
You must submit an ESSP for DDESB approval if the installation
is - ANSWER-Building an ES within an existing ESQD arc
Who must accept identified risks? - ANSWER-Installation
Commander