Erosion and Sedimentation Control
questions well answered already
passed
Which of the below would require an approved erosion and sedimentation control plan before
any clearing or grading may occur - correct answer ✔✔ Over 1 acre
Erosion and sedimentation control plans must be submitted how many days in advance of the
start of clearing or grading - correct answer ✔✔ 30 days
Which of the below are true about erosion and sedimentation control - correct answer ✔✔
Surfaces must be stabilized and sediment must be retained on site and don't start work before
plan approval
Who is responsible for erosion control - correct answer ✔✔ Person financially responsible for
land disturbing activity
In addition to the person financially responsible for the land disturbing activity who else may be
held responsible for erosion control - correct answer ✔✔ The land owner
After construction is complete who is responsible for maintenance and future compliance of
erosion control - correct answer ✔✔ Land owner
A permanent ground cover, sufficient to control erosion, must be installed within which of the
below times after completion of construction or development - correct answer ✔✔ 30 working
days or 120 calendar days
questions well answered already
passed
Which of the below would require an approved erosion and sedimentation control plan before
any clearing or grading may occur - correct answer ✔✔ Over 1 acre
Erosion and sedimentation control plans must be submitted how many days in advance of the
start of clearing or grading - correct answer ✔✔ 30 days
Which of the below are true about erosion and sedimentation control - correct answer ✔✔
Surfaces must be stabilized and sediment must be retained on site and don't start work before
plan approval
Who is responsible for erosion control - correct answer ✔✔ Person financially responsible for
land disturbing activity
In addition to the person financially responsible for the land disturbing activity who else may be
held responsible for erosion control - correct answer ✔✔ The land owner
After construction is complete who is responsible for maintenance and future compliance of
erosion control - correct answer ✔✔ Land owner
A permanent ground cover, sufficient to control erosion, must be installed within which of the
below times after completion of construction or development - correct answer ✔✔ 30 working
days or 120 calendar days