and Answers All Correct
The RBI Process is capable of generating? - Answer--a ranking by risk of all equipment
evaluated
-a detailed description of the inspection plan to by employed for each equipment
-a description of any other risk mitigation activities
Thinning causes the loss of material from - Answer-external or internal surfaces
The _____ of the data should be consistent with the RBI method used. - Answer-
precision
When some risks identified as acceptable then one of the following is not required. -
Answer-risk mitigation
An analysis that identifies and delineates the combinations of events and estimates the
frequency of occurrence for each combination and estimates the consequences. -
Answer-Quantitative risk analysis
Results of quantitative consequence analysis are usually expressed how? - Answer-
numerically
Reducing inspection costs is usually not the primary objective of
an__________________, but it is frequently a side effect of optimization:
a. RBI assessment
b. ALARP
c. HAZOP
d. risk analysis - Answer-RBI assessment
It is the reduction in the ability of a component to provide its intended purpose of
containment of fluids. - Answer-Deterioration
When inaccurate or insufficient failure data exists on the specific equipment item for
quantitative probability of failure analysis then: - Answer-general industry, company or
manufacturer failure used
The expected outcome from the application of the RBI process should be: - Answer-
Linking risk with appropriate inspection or other mitigation activities to manage risk