answers verified to pass 2025/2026
Real time transmission constraints or contingencies may be alleviated with
generators operating
A. below 60 Hz
B. on a new price curve
C. on a new cost curve
D. off cost (out of merit) - correct answer ✔D. off cost (out of merit)
What is the minimum size for a solar park to be required to have real and
reactive power telemetry ?
A. 1 MW
B. 3 MW
C. 5 MW
D. 7 MW - correct answer ✔B. 3 MW
PJM calls for which of the following to recover the ACE so that tie line
schedules are maintained ?
A. instantaneous reserve check
B. synchronized reserves
C. supplemental status report
D. minimum generation calculation - correct answer ✔B. synchronized
reserves
, If not cancelled by PJM , the minimum generation alert expires
A. at the end of the specified light load period
B. when notified by NERC
C. 12 hours after the alert was issued
D. after a 24hour period - correct answer ✔A. at the end of the specified light
load period
When PJM declares a hot weather alert , the generation dispatcher should
A. determine if maintenance can be deferred
B. notify transmission operators
C. direct all generating stations to increase MW output
D. direct all generating stations to reduce MVAR output . - correct answer
✔A. determine if maintenance can be deferred
During system restoration , the two categories of reserves are
A. dynamic and secondary
B. spinning and quick start
C. dynamic and spinning
D. spinning and primary - correct answer ✔C. dynamic and spinning
During system restoration , frequency should be maintained between
A. 59.50 and 60.00 Hz