A SWPPP Site Map will show all of the following except - correct
answer- Notices of Violation
Common types of erosion include all of the following except - correct
answer- Sedimentation
If your site is inspected by US EPA, or another regulatory agency, you
should: - correct answer- Be Courteous, Attend their inspection,
Allow access to site and documentation -- All of the above
Of the following factors that influence erosion rates, the one a
contractor has the most control over is: - correct answer-
Groundcover
Potential pollutant sources stored on a construction site may include -
correct answer- Petroleum storage tanks, soil amendments, masonry
materials -- all of the above
Proper spill management should include all of the following EXCEPT: -
correct answer- Installation of a spill pit on your construction sites