1. Slump is to be recorded to the nearest _______ mm. A) 1 B) 5
C) 10 D) 15 - correct answer -B) 5
2. The bowl of an air meter can be used for a density test. A) True
B) False - correct answer -A) True
3. The density of the concrete shall be reported to the nearest
________ kg. A) 0.1 B) 0.5 C) 1 D) 5 - correct answer -C) 1
4. A relative yield value of mire than 1.000 indicates the batch is
"short of it's designated volume". A) True B) False - correct
answer -B) False
, Page | 2
5. Core samples are to be submerged in water for ______ to
_____ hours immediately prior to the compression test. A) 8, 18
B) 16, 28 C) 32, 40 D) 40, 48 - correct answer -D) 40, 48
6. How accurate must the temperature measuring device be? A)
1.0 degrees Celsius B) 0.1 degrees Celsius C) 0.5 degrees
Celsius D) 5.0 degrees Celsius - correct answer -A) 1.0
degrees Celsius
7. How accurate must the reference thermometer be? A) 1.0
degrees Celsius B) 0.1 degrees Celsius C) 0.2 degrees Celsius
D) 0.5 degrees Celsius - correct answer -C) 0.2 degrees
Celsius
8. Calibration of the thermometer for testing freshly mixed
concrete must be compared between readings at least
________ apart. A)
9. 5.0 degrees Celsius B) 10 degrees Celsius C) 15 degrees
Celsius D) 20 degrees Celsius - correct answer -C) 15 degrees
Celsius
10. Once the slump cone has been filled and struck off, the
slump cone is to be lifted vertically in approximately
CCIL PRACTICE TEST BRAND
NEW OFFICIAL QUESTIONS
WITH ANSWERS.
1. Slump is to be recorded to the nearest _______ mm. A) 1 B) 5
C) 10 D) 15 - correct answer -B) 5
2. The bowl of an air meter can be used for a density test. A) True
B) False - correct answer -A) True
3. The density of the concrete shall be reported to the nearest
________ kg. A) 0.1 B) 0.5 C) 1 D) 5 - correct answer -C) 1
4. A relative yield value of mire than 1.000 indicates the batch is
"short of it's designated volume". A) True B) False - correct
answer -B) False
, Page | 2
5. Core samples are to be submerged in water for ______ to
_____ hours immediately prior to the compression test. A) 8, 18
B) 16, 28 C) 32, 40 D) 40, 48 - correct answer -D) 40, 48
6. How accurate must the temperature measuring device be? A)
1.0 degrees Celsius B) 0.1 degrees Celsius C) 0.5 degrees
Celsius D) 5.0 degrees Celsius - correct answer -A) 1.0
degrees Celsius
7. How accurate must the reference thermometer be? A) 1.0
degrees Celsius B) 0.1 degrees Celsius C) 0.2 degrees Celsius
D) 0.5 degrees Celsius - correct answer -C) 0.2 degrees
Celsius
8. Calibration of the thermometer for testing freshly mixed
concrete must be compared between readings at least
________ apart. A)
9. 5.0 degrees Celsius B) 10 degrees Celsius C) 15 degrees
Celsius D) 20 degrees Celsius - correct answer -C) 15 degrees
Celsius
10. Once the slump cone has been filled and struck off, the
slump cone is to be lifted vertically in approximately