100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

CCM Practice Exam Questions and Verified Answers

Rating
-
Sold
-
Pages
24
Grade
A+
Uploaded on
01-09-2025
Written in
2025/2026

CCM Practice Exam Questions and Verified Answers A. Contact utility companies early in the project life cycle; preferably during pre-design to determine all regulatory requirements, permitting, and provide all design documents and utility requirements B. Call the utility company a week before you need their work installed to keep your project moving. C. Invite representatives from the public utility companies to the pre-construction meeting D. Invite representatives from the public utility companies to attend regular progress meetings and practice ongoing partnering to accomplishing required tasks - correct answer The scope of work of the contract includes coordination with other entities, public utilities etc., entities over which neither you or the owner have any control, in order to complete the project. What strategies would be helpful to facilitate getting the necessary utility work done in a timely manner to avoid delays to the contractor? A. commissioning B. award C. notice to proceed (NTP) D. certification - correct answer The start of a construction project is initiated with what type of letter? A. Building Information Modeling B. PERT estimation technique C. Value engineering

Show more Read less
Institution
CCM - Contract And Commercial Management Certification
Course
CCM - Contract and Commercial Management Certification










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
CCM - Contract and Commercial Management Certification
Course
CCM - Contract and Commercial Management Certification

Document information

Uploaded on
September 1, 2025
Number of pages
24
Written in
2025/2026
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CCM Practice Exam Questions
and Verified Answers

A. Contact utility companies early in the project life cycle; preferably during pre-design to
determine all regulatory requirements, permitting, and provide all design documents and utility
requirements



B. Call the utility company a week before you need their work installed to keep your project
moving.



C. Invite representatives from the public utility companies to the pre-construction meeting



D. Invite representatives from the public utility companies to attend regular progress meetings
and practice ongoing partnering to accomplishing required tasks - correct answer ✔✔The scope
of work of the contract includes coordination with other entities, public utilities etc., entities
over which neither you or the owner have any control, in order to complete the project. What
strategies would be helpful to facilitate getting the necessary utility work done in a timely
manner to avoid delays to the contractor?



A. commissioning



B. award



C. notice to proceed (NTP)



D. certification - correct answer ✔✔The start of a construction project is initiated with what
type of letter?

,A. Building Information Modeling



B. PERT estimation technique



C. Value engineering



D. Monte Carlo analysis - correct answer ✔✔What is the term used for the project analysis
process used to determine how best to meet the necessary function, performance, and
reliability at the minimum life cycle cost?



A. covered under the owner's liability policy



B. included in commercial general liability coverage



C. excluded from commercial general liability coverage



D. covered under the self-insured policy that all firms carry - correct answer ✔✔Claims arising
out of professional negligence are typically:



A. Reject any claim that does not meet the specific notice provisions of the contract



B. Negotiate a settlement within 30 days of receiving each claim



C. Develop contemporaneous records and documentation

, D. Delay responding to all claims until legal council has reviewed documentation - correct
answer ✔✔Which of the following shows good construction management practice with respect
to claim mitigation?



A. Get the Contracting Officer to issue the least cost option to the contract



B. Work with the designer and contractor to try to identify cost and time saving alternatives and
present the options to the owner



C. Tell the owner he's crazy and it can't be done



D. Issue a change order immediately - correct answer ✔✔A major change in scope, requested
by the owner, will cause the project's budget and the contract completion date to be exceeded,
even though the owner has emphatically told you that no additional cost or time will be
authorized. What should the CM do?



A. The DRB provisions are not included in the contract



B. Board members are neutral



C. All parties agree on the selection of the board members



D. Board members are acknowledged technical experts - correct answer ✔✔A dispute has
arisen with the contractor and the owner wants to use a Dispute Review Board (DRB) to resolve
the issue. Which of the following issues will not allow the owner to use the DRB approach to
resolve the problem?



A. Drawings
$21.39
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
Stuvia71
3.0
(1)

Get to know the seller

Seller avatar
Stuvia71 Yale School Of Medicine
View profile
Follow You need to be logged in order to follow users or courses
Sold
1
Member since
3 months
Number of followers
1
Documents
1574
Last sold
2 months ago
ExamSavvy store

Looking for notes, comprehensive study guides, or insightful exam preparation materials,ExamSavvy is committed to making your study experience more efficient and effective. My goal is to simplify topics, break them down into digestible content and achieve academic success with latest update feel free to use my content and to give referals.

3.0

1 reviews

5
0
4
0
3
1
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions