What occurs when bids are revealed to create more competition? - ANSWER: Bid
Shopping
What benefits does an S corporation have? - ANSWER: prevent double taxation
How many weeks are employees entitled to under the Family Medical Leave Act -
ANSWER: 12 weeks
Federal Unemployment tax must be paid after an employee works ____ weeks -
ANSWER: 20 weeks
What is the debt ratio? - ANSWER: liabilities/assets
A contractor's license is needed when the residential project is valued over ___ -
ANSWER: $50,000
When is a contract considered accepted? - ANSWER: when signed
What is the most accurate method of estimate? - ANSWER: Quantity take off
method
Projects worth how much require bonds under the Miller Act? - ANSWER:
$100.000
LOUISIANA CONTRACTOR'S EXAM - BUSINESS AND
LAW EXAM|| ACCURATE AND FREQUENTLY TESTED
QUESTIONS AND 100% CORRECT ANSWERS WITH
RATIONALES|| LATEST AND COMPLETE UPDATE
WITH EXPERT VERIFIED SOLUTIONS|| SURE PASS!!
What occurs when bids are revealed to create more competition? - ANSWER: Bid
Shopping
What benefits does an S corporation have? - ANSWER: prevent double taxation
How many weeks are employees entitled to under the Family Medical Leave Act -
ANSWER: 12 weeks
Federal Unemployment tax must be paid after an employee works ____ weeks -
ANSWER: 20 weeks
What is the debt ratio? - ANSWER: liabilities/assets
A contractor's license is needed when the residential project is valued over ___ -
ANSWER: $50,000
When is a contract considered accepted? - ANSWER: when signed
What is the most accurate method of estimate? - ANSWER: Quantity take off
method
Projects worth how much require bonds under the Miller Act? - ANSWER:
$100.000