If you want to make changes to an estimate that has a status of completed, you must: -
Change the estimate status to In Progress.
Once a roof has been placed, the roof type can be changed in the _________ Window -
Properties
When an estimate is marked Completed, you can still modify it. - False
In some instances, you may leave items in violation if they are correct for the scope of
the estimate. - True
What variable can be used to place drip edge around the entire perimeter of a roof? - P
The Square Break tool can be used on roofs the same way it is used on rooms - True
If an overbuild roof is not a ________ of the main roof then those quantities will not be
calculated with the main roof. - subgroup
Roof InSight images help identify chimneys, rain gutters, roof vents, precise roof lines,
and roofing materials. - True
Roof InSight can be used to create a sketch of the exterior walls of a structure. - True
What is the Xactware Roof InSight Guarantee? - If for any reason you are not satisfied
with your Xactware Roof InSight, contact Xactware to receive a full credit.
You can request a Roof InSight from three different locations in Xactimate. Name the
locations. - 1. On Xactimate Dashboard
2.Under the Projects Tab
3.Within an Assignment
, Roof InSight is fully integrated with Xactimate, allowing you to make changes to the
Sketch that will be included in a printed report from Xactimate or XactAnalysis. - True
Where can you find the report included with the Roof InSight data package? - Estimate
Reports window > Documents tab > Attached Docs subtab
What information can be seen in the Projects Preview pane? - A preview of the selected
project's Sketch or notes.
List four items that can be transferred using the Data Transfer feature. - Macros,
Company Headers, Model Statements, Projects, Sketch Templates, etc.
Xactware publishes a full price list for every major identified pricing area in the United
States, ___, and ___. - Canada , United Kingdom
The ______ window lets you choose a report to print and then select options to use for
each report - Estimate Reports
What option lets you save a copy of y The only way to create an Xactimate estimate is
through XactAnalysis. - False
With an Internet connection, you can download and upload a XactAnalysis assignment.
- True
What are the steps in the 4-Step Estimating Process? - 1.Claim Info
2.Sketch
3.Estimate Items
4.Complete
It is mandatory to follow the 4-Step Estimating Process in its exact order. - False
At the fundamental level of learning, it is recommended to add or create a project from
the Control Center tab. - False
Multiple addresses can be added through Insured Info. - True
There are three coverage types available in the Coverage/Loss section. Name them - a.
Dwelling
b. Other Structures
c. Contents
A deductible can be applied across all coverages or specific coverage only - True