Upon completion of the following tasks, what should the interior
designer do NEXT? • Interview client. • Obtain architectural
drawings. • Conduct a site inspection. • Prepare preliminary
sketches. • Evaluate existing furniture for continued use. -
correct answer Review preliminary specifications with the
manufacturer's representatives.
What is the MOST important criterion to consider in selecting a
specialized consultant to work as part of an effective design team?
-The consultant's professional qualifications
-How the consultant will personally fit as part of the design team
-The consultant's past experience working on similar projects
-The consultant's current workload and schedule -
correct answer The consultant's professional qualifications
Why does the HVAC system need to be balanced at the end of a
commercial project?
-To verify that air quality levels are within the design specifications
-To detect significant air leaks in ductwork
-To adjust air flow at each device location to meet the criteria in the
engineer's design
, IDPX Project Coordination Exam
Questions And Answers
-To determine that each office is receiving the amount of outside
air required by the design -
correct answer -To adjust air flow at each device location to
meet the criteria in the engineer's design
designer would be most likely to suggest to a technical engineer
that additional ventilation or exhaust be provided in a
private toilet room
commercial kitchen
corporate conf room
exercise room -
correct answer corporate con room - all others have exhaust
governed by local building codes
latest possible starting time is found in which of the following
schedules/charts
CPM chart
full-wall schedule
Gantt chart
workflow schedule -
correct answer CPM chart
Questions And Answers
Upon completion of the following tasks, what should the interior
designer do NEXT? • Interview client. • Obtain architectural
drawings. • Conduct a site inspection. • Prepare preliminary
sketches. • Evaluate existing furniture for continued use. -
correct answer Review preliminary specifications with the
manufacturer's representatives.
What is the MOST important criterion to consider in selecting a
specialized consultant to work as part of an effective design team?
-The consultant's professional qualifications
-How the consultant will personally fit as part of the design team
-The consultant's past experience working on similar projects
-The consultant's current workload and schedule -
correct answer The consultant's professional qualifications
Why does the HVAC system need to be balanced at the end of a
commercial project?
-To verify that air quality levels are within the design specifications
-To detect significant air leaks in ductwork
-To adjust air flow at each device location to meet the criteria in the
engineer's design
, IDPX Project Coordination Exam
Questions And Answers
-To determine that each office is receiving the amount of outside
air required by the design -
correct answer -To adjust air flow at each device location to
meet the criteria in the engineer's design
designer would be most likely to suggest to a technical engineer
that additional ventilation or exhaust be provided in a
private toilet room
commercial kitchen
corporate conf room
exercise room -
correct answer corporate con room - all others have exhaust
governed by local building codes
latest possible starting time is found in which of the following
schedules/charts
CPM chart
full-wall schedule
Gantt chart
workflow schedule -