100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

QSP FINAL EXAM STUDY GUIDE 2025/2026 COMPLETE QUESTIONS WITH CORRECT DETAILED SOLUTIONS ||ALREADY GRADED!!! 100% GUARANTEED PASS <BRAND NEW VERSION>

Rating
-
Sold
-
Pages
11
Grade
A+
Uploaded on
19-07-2025
Written in
2024/2025

QSP FINAL EXAM STUDY GUIDE 2025/2026 COMPLETE QUESTIONS WITH CORRECT DETAILED SOLUTIONS ||ALREADY GRADED!!! 100% GUARANTEED PASS &lt;BRAND NEW VERSION&gt; 1. A storm that produces ½ inch or more of precipitation, with a 48 hour or greater period between rain events is a/an... a. Qualifying rain event b. Extended storm event c. Inactive storm event d. Unsafe monitoring event - ANSWER A 2. Upload photos to SMARTS that are taken during daily inspections of the LUP site before, during, and after every ___ storm event a. First b. Second c. Third d. Fourth - ANSWER C 3. Which statement is false? Monitoring is not required when: a. the site/sampling locations are unsafe to access due to the storm event b. it is outside of scheduled site operation hours c. the contractor elects not to work and the site is "shut down" for a rainy day - ANSWER C 4. What is the Numeric Action Level (NAL) for pH? a. 3.5-5.5 b. 6.0-9.0 c. 6.5-8.5 d. 9.0-12.0 - ANSWER C 5. What is the exceedance trigger for Receiving Water Monitoring? a. 100 NTU b. 250 NTU c. 500 NTU d. 1,000 NTU - ANSWER C 6. What system that uses chemical coagulation, chemical flocculation, or electro-coagulation to reduce turbidity? a. ATS b. CGP c. CWA d. NAL - ANSWER A 7. If the R Factor is ____, you can apply for the Erosivity Waiver. a. 1 b. Less than 1 c. 5 d. Less than 5 - ANSWER D 8. The R factor accounts for: a. Project location, length of construction period, and time of year b. Project schedule c. Historical rain events d. Potential pollutants on site - ANSWER A 9. Which risk level must electronically submit all storm event sampling results to State Water Board no later than 5 days after the conclusion of the storm event? a. Risk Level 1 b. Risk Level 2 c. Risk Level 3 d. All Risk Levels - ANSWER C 10. Which statement is true? Risk Level 2 sites: a. Are subject to all Risk Level 3 requirements b. Must electronically submit all NAL exceedance storm event sampling results to State Water Board no later than 10 days after the storm event c. Have 10 categories of year-round minimum BMP's d. Do not need to manage run-on or run-off controls - ANSWER B 11. The REAP must be onsite during construction and available a. for a minimum of 1 Year b. for a minimum of 3 Years c. 72 hours prior to any likely precipitation event d. Until the end of the construction project - ANSWER B 12. NEL Violation Reports must be submitted to State Board within 24 hours after exceedance has been identified. NEL's are only subject to: a. Risk Level1 b. Risk Level 2 c. Risk Level 3 d. ATS Sites only - ANSWER D 13. TRUE OR FALSE: All Annual Reports, or other information required by the General Permit (other than PRDs and NOTs) or requested by the Regional Water Board, State Water Board, U.S. EPA, or local stormwater management agency shall be certified and submitted by the QSD - ANSWER False (LRP or LRP's Approved Signatory) 14. TRUE OR FALSE:LID's goal is to mimic a site's predevelopment hydrology by using design and techniques that infiltrate, store, evaporate, and detain runoff close to its source. - ANSWER True 15. Hydrologic source controls are a design technique that minimize and/or slow the rate of stormwater runoff from the site. Examples include: a. Reduction of pervious surfaces b. Use of landscaping as a storm drain treatment feature c. Drain rooftop downspouts to impervious areas d. Stormwater treatment facility - ANSWER B 16. TRUE OF FALSE:LUP projects are subject to postconstruction requirements due to the nature of their construction to return project sites to preconstruction conditions. - ANSWER False 17. Which statement is false? Bioassessment monitoring is required for projects that meet all of the following, EXCEPT: a. Rated Risk Level 3/ LUP Type 3 b. Directly discharges runoff to a freshwater wadeable stream that is sediment impaired and has beneficial uses for cold, migratory, and spawn c. Requires post-construction storm water treatment d. Total project-related ground disturbance exceeds 30 acres - ANSWER C 18. Project sediment risk is: a. the relative amount of sediment that can be discharged, driven largely by scheduling and site characteristics b. the risk sediment discharges pose to the receiving waters. - ANSWER A 19. TRUE OR FALSE: Discharges located within the watershed of an impaired water body, for which a TMDL for sediment has been adopted by the Regional Water Board or USEPA, must comply with the approved TMDL if it identifies "construction activity" or land disturbance as a source of sediment - ANSWER True

Show more Read less
Institution
QSP - Qualified SWPPP Practitioner
Course
QSP - Qualified SWPPP Practitioner









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
QSP - Qualified SWPPP Practitioner
Course
QSP - Qualified SWPPP Practitioner

Document information

Uploaded on
July 19, 2025
Number of pages
11
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

QSP FINAL EXAM STUDY GUIDE
2025/2026 COMPLETE QUESTIONS WITH
CORRECT DETAILED SOLUTIONS
||ALREADY GRADED!!! 100%
GUARANTEED PASS <BRAND NEW
VERSION>
1. A storm that produces ½ inch or more of precipitation, with a 48
hour or greater period between rain events is a/an...
a. Qualifying rain event
b. Extended storm event
c. Inactive storm event
d. Unsafe monitoring event - ANSWER ✓ A

2. Upload photos to SMARTS that are taken during daily inspections
of the LUP site before, during, and after every ___ storm event
a. First
b. Second
c. Third
d. Fourth - ANSWER ✓ C

3. Which statement is false? Monitoring is not required when:
a. the site/sampling locations are unsafe to access due to the
storm event
b. it is outside of scheduled site operation hours
c. the contractor elects not to work and the site is "shut down"
for a rainy day - ANSWER ✓ C

4. What is the Numeric Action Level (NAL) for pH?
a. 3.5-5.5

, b. 6.0-9.0
c. 6.5-8.5
d. 9.0-12.0 - ANSWER ✓ C

5. What is the exceedance trigger for Receiving Water Monitoring?
a. 100 NTU
b. 250 NTU
c. 500 NTU
d. 1,000 NTU - ANSWER ✓ C

6. What system that uses chemical coagulation, chemical
flocculation, or electro-coagulation to reduce turbidity?
a. ATS
b. CGP
c. CWA
d. NAL - ANSWER ✓ A

7. If the R Factor is ____, you can apply for the Erosivity Waiver.
a. 1
b. Less than 1
c. 5
d. Less than 5 - ANSWER ✓ D

8. The R factor accounts for:
a. Project location, length of construction period, and time of
year
b. Project schedule
c. Historical rain events
d. Potential pollutants on site - ANSWER ✓ A

9. Which risk level must electronically submit all storm event
sampling results to State Water Board no later than 5 days after the
conclusion of the storm event?
a. Risk Level 1

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
SmartscoreAaron Chicago State University
View profile
Follow You need to be logged in order to follow users or courses
Sold
36
Member since
1 year
Number of followers
3
Documents
3038
Last sold
1 week ago
SMARTSCORES LIBRARY

Get top-tier academic support for Psychology, Nursing, Business, Engineering, HRM, Math, and more. Our team of professional tutors delivers high-quality homework, quiz, and exam assistance—ensuring scholarly excellence and grade-boosting results. Trust our collaborative expertise to help you succeed in any course at U.S.A Institutions.

3.8

4 reviews

5
2
4
1
3
0
2
0
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions