OBJECTIVE ASSESSMENT FINAL EXAM
2025/2026 COMPLETE QUESTIONS AND
CORRECT DETAILED ANSWERS WITH
RATIONALES || 100% GUARANTEED
PASS!! <<brAND NEW VERSION>>
1. Physical Task Dependency - ANSWER ✓ Task dependency where
one activity cannot happen until something else is completed (i.e.
primer applied before paint) Pg 112
2. Label Node - ANSWER ✓ A classification system such as 1.1, 1.2,
etc Pg 113
3. Finish-to-Start Relationships (FS) - ANSWER ✓ a logical
relationship in which a successor activity cannot start until a
predecessor has finished. Pg 114
4. Finish-to-Finish Relationships (FF) - ANSWER ✓ A logical
relationship where the successor task cannot be completed until the
first task is completed. Pg 114
5. Start-to-Start Relationships (SS) - ANSWER ✓ A logical, but less
common, relationship where the successor activity cannot start
until the predecessor activity has started Pg 114
,6. Start-to-Finish Relationships - ANSWER ✓ A logical, but less
common, relationship where the first task cannot end until the
second task has started Pg 114
7. Lag Time - ANSWER ✓ A delay that makes the successor task
start some time after its predecessor ends Pg 115
8. Float/Slack - ANSWER ✓ the amount of time an activity, network
path, or project can be delayed from the early start without
changing the completion date of the project. Pg 117
9. Total float - ANSWER ✓ The difference between the finish date of
the last activity on the critical path and the project completion date.
Pg 117
10. negative float - ANSWER ✓ the calculated completion date
of the last activity is later than the targeted completion date
established at the beginning of the project. Pg 117
11. free float - ANSWER ✓ Free float is the amount of time an
activity can be delayed without delaying the Early Start of its
successor activity.
12. forward pass - ANSWER ✓ start assigning dates based on the
earliest start date, adding dates based on our estimates for each task
in the diagram. Pg 117
13. backward pass - ANSWER ✓ Refers to the calculation of late
finish dates and late start dates for the portions of schedule
activities that have not been completed. Pg 117
,14. crash - ANSWER ✓ to obtain the greatest amount of
compression of the schedule/critical path for the least incremental
cost or time. Pg 117
15. critical chain - ANSWER ✓ builds on the critical path
method by going a step further adding time buffers to account for
limited resources. Pg 117
16. Co-located Teams - ANSWER ✓ team members physically
working at the same location or holding project meetings together
in a common setup. Pg 125
17. earned value analysis (EVA) - ANSWER ✓ the process of
assessing the work completed. Pg 128
18. Identify Change - ANSWER ✓ Which change process step is
described: Processes are in place to document changes as soon as
they are identified Pg 131
19. Evaluate Change - ANSWER ✓ Which change process step
is described: The appropriate stakeholders provide input to identify
cost and benefits Pg 131
20. Communicate Change - ANSWER ✓ Which change process
step is described: Project plans are updated to incorporate the
change Pg 131
21. Variance - ANSWER ✓ The fact or quality of being
different, divergent, or inconsistent. Pg 132
22. Earned Value Management (EVM) - ANSWER ✓ A widely
accepted method of measuring project performance and progress of
actual cost against the budgeted/planned cost. Pg 135
, 23. Earned Value (EV) - ANSWER ✓ The dollar value of all
work completed to date which is based on the baseline budgeted
cost of each activity. Pg 135
24. Planned Value (PV) - ANSWER ✓ The dollar value of all
work scheduled to have been completed to date which is based on
the baseline schedule and the calendarized baseline budget. Pg 135
25. Actual Cost (AC) - ANSWER ✓ The total dollar value of
costs incurred to date which includes work and invoices already
paid as well as any expenses that have been incurred but not yet
invoiced or paid. Pg 135
26. Budget at Completion (BAC) - ANSWER ✓ the approved
total baseline budget approved for the completed project. Pg 135
27. 50-50 rule - ANSWER ✓ Assigns half completed as soon as
an activity is started and fully completed when an acitivity is
finished. Pg 135
28. 0-100 rule - ANSWER ✓ Assigns no portion completed until
an activity is finished, then it assigns the full portion completed Pg
135
29. Cost variance (CV) - ANSWER ✓ Compares the difference
between the EV and the AC (EV - AC) to determine if the project
is meeting its budget expectations. Pg 136
30. Schedule variance (SV) - ANSWER ✓ Compares differences
between the EV and the PV (EV - PV) to determine if the project is
meeting its schedule expectations or if there is a variance. Pg 136