A) Increase Net Interchange Schedule by 20 MWs. - ANS The Reliability Coordinator just informed you of a slow time error correction which will begin at the top of the next hour. Your EMS system will not let you change your scheduled frequency. Your Frequency Bias Setting is - 100 MW/.1Hz. What action should you take? A) Increase Net Interchange Schedule by 20 MWs. B) Inform the Reliability Coordinator that you cannot participate in the time error correction. C) Decrease Net Interchange Schedule by 20 MWs. D) Increase Net Interchange Schedule by 10 MWs. SOS NERC PREP – RELIABILITY EXAM 2025 QUESTIONS AND ANSWERS 2 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED. C) 1 & 4 - ANS A Balancing Authority has a sudden loss of a large block of load in its area. This loss will be seen instantaneously in the change of which of the following values? 1. Actual Net Interchange 2. Scheduled Frequency 3. Scheduled Net Interchange 4. Area Control Error A) 4 only B) 1 & 3 C) 1 & 4 D) 3 & 4 A) Tie lines readings - ANS Metered Data included in the calculation of ACE are: dynamic schedules, pseudo ties, actual frequency, and all __________. A) Tie lines readings B) Generators output 3 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED. C) Scheduled frequency indications D) Transformer load A) -100 - ANS Balancing Authority A is currently reading a system frequency of 60.00 Hz. Its Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +200 MW. If Balancing Authority A's frequency bias setting is 100 MW/0.1 Hz, what is ACE? A) -100 B) 0 C) 10 D) 100 B) 25 MWs in - ANS A Balancing Authority has a Net Interchange Schedule of -250 MWs from 1200 to 1600 on a summer day. The Net Interchange Actual for those same hours respectively were -230 MW, -275 MW, -250 MW and -270 MW. What was the Balancing Authority's Inadvertent Interchange for the 4-hour period? A) 6 MWs out 4 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED. B) 25 MWs in C) 25 MWs out D) 6 MWs in D) Tie lines - ANS For the ACE equation to work properly, dynamic schedules, pseudo ties, frequency, and all ________________ must be metered. A) Generation B) Communications C) Transformers D) Tie lines B) The ACE will be a negative value and AGC will increase generation - ANS If the frequency bias setting is set to a less negative value than the frequency response of a Balancing Authority and a frequency increase is caused by a sudden loss of load in an external balancing area, what will be the result? A) The ACE will be zer

Show more Read less
Institution
SOS NERC
Course
SOS NERC











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
SOS NERC
Course
SOS NERC

Document information

Uploaded on
July 13, 2025
Number of pages
134
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

SOS NERC PREP – RELIABILITY EXAM
2025 QUESTIONS AND ANSWERS




A) Increase Net Interchange Schedule by 20 MWs. - ANS The Reliability Coordinator just

informed you of a slow time error correction which will begin at the top of the next hour. Your

EMS system will not let you change your scheduled frequency. Your Frequency Bias Setting is -

100 MW/.1Hz. What action should you take?




A) Increase Net Interchange Schedule by 20 MWs.




B) Inform the Reliability Coordinator that you cannot participate in the time error correction.




C) Decrease Net Interchange Schedule by 20 MWs.




D) Increase Net Interchange Schedule by 10 MWs.




1 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED.

,C) 1 & 4 - ANS A Balancing Authority has a sudden loss of a large block of load in its area. This

loss will be seen instantaneously in the change of which of the following values?




1. Actual Net Interchange


2. Scheduled Frequency


3. Scheduled Net Interchange


4. Area Control Error




A) 4 only


B) 1 & 3


C) 1 & 4


D) 3 & 4




A) Tie lines readings - ANS Metered Data included in the calculation of ACE are: dynamic

schedules, pseudo ties, actual frequency, and all __________.




A) Tie lines readings


B) Generators output

2 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED.

,C) Scheduled frequency indications


D) Transformer load




A) -100 - ANS Balancing Authority A is currently reading a system frequency of 60.00 Hz. Its

Net Actual Interchange is +100 MW and its Net Scheduled Interchange is +200 MW. If Balancing

Authority A's frequency bias setting is 100 MW/0.1 Hz, what is ACE?




A) -100


B) 0


C) 10


D) 100




B) 25 MWs in - ANS A Balancing Authority has a Net Interchange Schedule of -250 MWs from

1200 to 1600 on a summer day. The Net Interchange Actual for those same hours respectively

were -230 MW, -275 MW, -250 MW and -270 MW. What was the Balancing Authority's

Inadvertent Interchange for the 4-hour period?




A) 6 MWs out



3 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED.

, B) 25 MWs in


C) 25 MWs out


D) 6 MWs in




D) Tie lines - ANS For the ACE equation to work properly, dynamic schedules, pseudo ties,

frequency, and all ________________ must be metered.




A) Generation


B) Communications


C) Transformers


D) Tie lines




B) The ACE will be a negative value and AGC will increase generation - ANS If the frequency

bias setting is set to a less negative value than the frequency response of a Balancing Authority

and a frequency increase is caused by a sudden loss of load in an external balancing area, what

will be the result?




A) The ACE will be zero and will take no AGC action


4 Copyright ©2025 FYNDLAY ALL RIGHTS RESERVED.

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
Fyndlay Kaplan University
View profile
Follow You need to be logged in order to follow users or courses
Sold
352
Member since
1 year
Number of followers
80
Documents
18285
Last sold
1 week ago
Scholar\'s Sanctuary.

Explore a Vast Collection of Finely Made Learning Materials.

3.7

68 reviews

5
32
4
8
3
13
2
6
1
9

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions