NERC CNP PRACTICE TEST 2025/2026 QUESTIONS AND VERIFIED ANSWERS//GRADED A +

Institution
NERC CNP PRACTICE
Course
NERC CNP PRACTICE











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
NERC CNP PRACTICE
Course
NERC CNP PRACTICE

Document information

Uploaded on
July 3, 2025
Number of pages
69
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

SOS NERC Prep - RELIABILITY EXAM QUESTIONS & ANSWERS

The Reliability Coordinator just informed you of a slow time error correction
which will begin at the top of the next hour. Your EMS system will not let you
change your scheduled frequency. Your Frequency Bias Setting is -100 MW/.1Hz.
What action should you take?

A) Increase Net Interchange Schedule by 20 MWs.

B) Inform the Reliability Coordinator that you cannot participate in the time error
correction.

C) Decrease Net Interchange Schedule by 20 MWs.

D) Increase Net Interchange Schedule by 10 MWs. - A) Increase Net Interchange
Schedule by 20 MWs.

A Balancing Authority has a sudden loss of a large block of load in its area. This
loss will be seen instantaneously in the change of which of the following values?

1. Actual Net Interchange
2. Scheduled Frequency
3. Scheduled Net Interchange
4. Area Control Error

A) 4 only
B) 1 & 3
C) 1 & 4
D) 3 & 4 - C) 1 & 4

Metered Data included in the calculation of ACE are: dynamic schedules, pseudo
ties, actual frequency, and all __________.

A) Tie lines readings
B) Generators output
C) Scheduled frequency indications




1

,D) Transformer load - A) Tie lines readings

Balancing Authority A is currently reading a system frequency of 60.00 Hz. Its Net
Actual Interchange is +100 MW and its Net Scheduled Interchange is +200 MW. If
Balancing Authority A's frequency bias setting is 100 MW/0.1 Hz, what is ACE?

A) -100
B) 0
C) 10
D) 100 - A) -100

A Balancing Authority has a Net Interchange Schedule of -250 MWs from 1200 to
1600 on a summer day. The Net Interchange Actual for those same hours
respectively were -230 MW, -275 MW, -250 MW and -270 MW. What was the
Balancing Authority's Inadvertent Interchange for the 4-hour period?

A) 6 MWs out
B) 25 MWs in
C) 25 MWs out
D) 6 MWs in - B) 25 MWs in

For the ACE equation to work properly, dynamic schedules, pseudo ties,
frequency, and all ________________ must be metered.

A) Generation
B) Communications
C) Transformers
D) Tie lines - D) Tie lines

If the frequency bias setting is set to a less negative value than the frequency
response of a Balancing Authority and a frequency increase is caused by a sudden
loss of load in an external balancing area, what will be the result?

A) The ACE will be zero and will take no AGC action

B) The ACE will be a negative value and AGC will increase generation



2

,C) The ACE will be a positive value and AGC will lower generation

D)This will not affect the ACE - B) The ACE will be a negative value and AGC
will increase generation

If the frequency bias setting is less negative than the frequency response of a
Balancing Authority and a frequency decline is caused by a sudden loss of
generation in an external balancing area, what will be the result?

A) The ACE will be a negative value and AGC will increase generation.

B) This will not affect the ACE.

C) The ACE will be a positive value and AGC will lower generation.

D) The ACE will be zero and will take no AGC action. - C) The ACE will be a
positive value and AGC will lower generation.

It is the responsibility of which entity/entities to develop, maintain, and implement
load shedding plans?

A) Transmission Operators and Balancing Authorities

B) Reliability Coordinator

C) Load Serving Entities

D) Balancing Authority - A) Transmission Operators and Balancing Authorities

A Transmission line is loaded 25% above its SOL. A parallel line is out for routine
maintenance and can be placed in service in 10 minutes. What is the first step the
Operator should take to reduce the line loading?

A)Shed load at the downstream bus.




3

, B) Open the line.

C) Re-Dispatch Generation.

D) Initiate the restoration of the parallel line. - D) Initiate the restoration of the
parallel line.

As a Transmission Operator, you realize that the voltage level is starting to decline
in the North West part of the system. Which of the following devices should you,
as a Transmission Operator, be able to operate, and/or have another entity operate
to raise the voltage level back to normal in the North West part of the system?

A) Transformer Underload Tap Changers
B) Shunt Capacitor Banks
C) Generator Reactive Output
D) All answers are correct - D) All answers are correct

Voltage reduction for load relief should be made on the __________.

A) Distribution system
B) Entire Interconnection simultaneously
C) Tie-lines with other Balancing Authority Areas
D) Transmission System - A) Distribution system

Under Frequency Load Shedding (UFLS) is to stabilize the imbalance between
generation and load that has been created by a system disturbance. This is
accomplished by ____________.

A) Tripping generation first
B) Voltage reduction on the distribution system.
C) Shedding all load to arrest frequency
D) Shedding load prior to generation tripping - D) Shedding load prior to
generation tripping




4

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
ANSWERSHEET Teachme2-tutor
View profile
Follow You need to be logged in order to follow users or courses
Sold
43
Member since
1 year
Number of followers
6
Documents
361
Last sold
1 month ago
ANSWERSHEET

LEARNING CAN ALSO BE EXCITING! Home of Champions its time to provide THE ANSWERSHEET Welcome to Answersheet, your go-to source for high-quality test banks and study materials designed to help you excel academically. We offer a comprehensive range of resources including test banks, study guides, solution manuals,Exams ,NASM , and other study materials, all meticulously curated to ensure accuracy and effectiveness. Our affordable, instantly accessible materials are complemented by excellent customer support, making your learning experience seamless and efficient. Walk with Answersheet to be your partner in academic success, providing the tools you need to achieve your educational enjoy sucess in academics

Read more Read less
2.0

4 reviews

5
0
4
0
3
2
2
0
1
2

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions