FINAL ESTIMATES LEVEL 2 EXAM 2025 |
CERTIFIED QUESTIONS WITH ANSWERS
If the Resident Office receives an unpaid bill notice, what should the Resident
Office do? - Correct-answer-A)Respond in writing to the Prime Contractor
B)Send a copy to the DFEM
C)Copy the Subcontractor
ALL OF THE ABOVE
On a dual FIN Project under one Contract: Project A has 20,000 tons and Project
B has 25,000 tons. the total tonnage for the contract =45,000 tons. The tonnage
placed for the month=4525 tons. Determine how many tons should be reported
on each project for this month. - Correct-answer-A) 20,000/45,000 =0.444 X 4525
Tons= 2011.1 TNS
B) 25,000/45,000 = 0.556 X 4525 Tons= 2513.9 TNS
On a new construction project, the length of conduit for a signalization job
located under a utility strip & between the back of curb and front of sidewalk is
paid for as ? - Correct-answer-As underground conduit.
, 2|Page
On design build Contracts, the Contractor will receive monthly progress
payments based on? - Correct-answer-Monthly Estimates
On Conventional jobs, concrete class IV (superstructure) methos of measurement
is? - Correct-answer-Plan Quantities
Using the Current Specifications and the attached Summary Tables what is the
pay quantity for the concrete production pile? (80' authorized pile length) -
Correct-answer-80 ft
Determine the adjusted plan quantity tonnage and the maximum tonnage that
can be paid for Miscllaneous Asphalt based on the current Specifications, which
allows a maximum pay of 105% of the adjusted plan quantity tons. ( pay to the
appropriate accuracy)
Plan Quantity Area (SY) =700 SY ( no revisions)
Plan Quantity Tons: 70.0 Tons based on 2" thick per specs
Adjusted PQ Tonnage Placed =75.2 Tons from report
Gmm fromSpecs = 2.540 and Target Spread Rate =220 Lbs/SY
Gmm from Mix 1: 2.522 and tonnage- weighted Gmm=2.55 Lbs/SY - Correct-
answer-69.5 Tons and max pay 73.0 Tons