1. All of the following are Physi- Bioremediation
cal Pollutant removal
mecha- nisms except:
2. The is ultimately respon- Property Owner
sible for the
performance of the
stormwater pollution
prevention plan on the
site
3. The benefit of Reduces Evaporation
mulching in- cludes
4. Which of the following Temperature and pH
af- fects the speed of
chemical reactions and
rate of biolog- ical
growth which may
affect removal of
pollutants:
5. When should a Notice of Ter- When construction has ceased and the site is stable
with vege-
mination(NOT) be filed? tative growth
6. Bioaccumulation is an Toxins
effect of which pollutant:
7. Which of the following a. restore and maintain the chemical, biological, and
are purposes of the physical integrity
CWA b. maintain waters to be fishable and swimmable
c. consider other uses and values of public waters
, CPSWQ Exam Solved Correctly To Score A+
8. Which equation is commonly Manning's Equation
used to estimate velocity for
channel flow:
, CPSWQ Exam Solved Correctly To Score A+
9. Manning's Equation hydraulic equation which defines the relationship in open
chan-
nels between a stream's velocity and its slope and depth
10. Pollutant concentrations Long Term
are best used to evaluate
effects
Agricultural
11. This land use category
has the highest BOD
concentra- tions:
Pathogens
12. This pollutant is a result
of E. Coli
13. What does SMP stand for Stormwater Management Practice
14. A treats a need to create a SWPPP for
portion of the water NPDES compliance?
quality volume by
detaining storm flows
for a specified
minimum time
15. There are 5 commercial
con- struction sites with
4 sites containing over 1
acre, and 1 site that is
only 0.8 acres. All sites
are being construct- ed
in the same area next to
each other but by
different contractors.
How many sites will
, CPSWQ Exam Solved Correctly To Score A+
Extended Detention Pond
5
16. Nutrients