Exam Questions and CORRECT Answers
How many samples are required to create a composite sample? - CORRECT ANSWER -3
samples
When core sampling, where should nuclear density gauge test be taken? - CORRECT
ANSWER - Test should be taken prior to coring in same location
What is a "Lot" comprised of? - CORRECT ANSWER - A lot is split up in 5 different
samples called "Sublots"
When sampling from a paver auger, where should the sample be taken? - CORRECT
ANSWER - Sample should be taken from the end of the auger
When sampling from roadway, where should sample be taken? - CORRECT ANSWER -
Immediately behind paver and Infront of breakdown roller
When sampling from roadway, how far away should rollers stay away? - CORRECT
ANSWER - Rollers should be 10' away from sampling area
When sampling from the roadway, what're the type of sampling methods? - CORRECT
ANSWER - Plate with cookie cutter, Plate method, non-plate method
What is the requirement when using plate method for sampling from roadway? - CORRECT
ANSWER - 1. Plate is placed 10' Infront of paver and at least 2' on the inside edge of the
mat
2. 3 samples must be acquired
What are the requirements when sampling from a paver? - CORRECT ANSWER - 1. Trim
8-12" before taking sample
, 2. Remove 6-10" of material in center of hopper
3. Take sample directly into vertical face
What are the requirements for sampling from stockpiles? - CORRECT ANSWER - 1.
Remove 4" of outermost layer
2. Obtain sample as close as possible to the intersection of horizontal and vertical face.
How many sections should be split from a sample container when " sample splitting"? -
CORRECT ANSWER -4
What are the requirements for sampling from a loaded truck? - CORRECT ANSWER - 1.
Truck should be split into 4 different quadrants
2. Remove 4" of outermost layer
3. 3 increments placed on sample container
What is open-graded Asphalt? - CORRECT ANSWER - Top course permeable layer that
supports drainage, tire dampening and road spray
What is dense-graded Asphalt? - CORRECT ANSWER - Base or binder course that have
larger nominal size aggregates. Low water impermeability, strength and improves freeze/thaw
cycles
Existing surface preparation inspection: Structurally Sound - CORRECT ANSWER -
Cracks and other structural defects must be prepared to minimize reflective cracking. surface
must be non-compressible and capable of bearing traffic loads
Existing surface preparation: Well Drained - CORRECT ANSWER - 1. Surface must not
be undermined by water intrusion.
2. Water should not collect around roadbed
3. Roadbed should promote positive drainage