Which of the following does the Government provide to a
contractor and is consumed in performance of the contract?
- Government-Furnished Equipment
- Government-Furnished Material
- Contractor-Acquired Property
- None of the above - Correct Answer ✔ ✔ GFM
Material is property that may be consumed or expended
during the performance of a contract and does not include
,equipment, special tooling, special test equipment or real
property. See FAR 45.101.
This is documentation such as manuals, drawings and test
data provided by the Government to potential offerors. -
Correct Answer ✔ ✔ Government-Furnished Information
These are items provided by the government to potential
offerors. See FAR 7.105(b)(16).
No separate justification or determination and findings is
required to set aside a contract action for small business
concerns.
True or False - Correct Answer ✔ ✔ True
,FAR 6.203(b)
What are the four primary appropriations used in contracting?
- Correct Answer ✔ ✔ O&M, RDT&E, Procurement, and
MILCON
Do you remember what two broad categories our evaluation
factors must fall into when contracting by negotiation?" -
Correct Answer ✔ ✔ cost/price and the quality of the
product or service shall be addressed with one or more non-
cost evaluation factors.
Where in the FAR are evaluation criteria addressed when
using Contracting by Negotiation? - Correct Answer ✔ ✔
Within FAR part 15 - Contract by Negotiation
, FAR 15.304
If your requirement is clearly definable and successful
contract performance is practically certain to occur the
following will likely play a dominant role in the source
selection: - Correct Answer ✔ ✔ Cost or Price
See FAR 15.101, which states that if the requirement is clearly
definable and the risk of unsuccessful contract performance is
minimal, cost or price may play a dominant role in source
selection.
True or False. Delivery or performance incentives are
authorized on a FFP contract. - Correct Answer ✔ ✔ True.