ICC General Requirements Exam
Questions with correct Answers 2025/2026
A+ Graded 100% Verified
It is the responsibility of the ______________ to monitor the special inspection activities. -
ANS-The building official
The ______________ is responsible for approving the special inspection program. - ANS-The
building official
Who does the special inspector notify first if there is a non-conforming item? - ANS-The
inspection supervisor
How often does the special inspector submit reports to the building official? - ANS-As
determined by the building official
Who establishes the special inspection program? - ANS-The building department
Who submits the statement of responsibility? - ANS-The contractor
Who produces the statement of responsibility? - ANS-The contractor
A preconstruction meeting is: - ANS-Initiated by the general contractor
The responsibility of ensuring that day to day work is covered by inspections falls on - ANS-The
contractor
The ______________ is responsible for approving the special inspection program. - ANS-The
building official
Who establishes the special inspection program? - ANS-The building department
What does the special inspection agreement state? - ANS-The owner or registered design
professional hired an approved special inspection agency
Who notifies the special inspector of upcoming inspection tasks? - ANS-The contractor
Questions with correct Answers 2025/2026
A+ Graded 100% Verified
It is the responsibility of the ______________ to monitor the special inspection activities. -
ANS-The building official
The ______________ is responsible for approving the special inspection program. - ANS-The
building official
Who does the special inspector notify first if there is a non-conforming item? - ANS-The
inspection supervisor
How often does the special inspector submit reports to the building official? - ANS-As
determined by the building official
Who establishes the special inspection program? - ANS-The building department
Who submits the statement of responsibility? - ANS-The contractor
Who produces the statement of responsibility? - ANS-The contractor
A preconstruction meeting is: - ANS-Initiated by the general contractor
The responsibility of ensuring that day to day work is covered by inspections falls on - ANS-The
contractor
The ______________ is responsible for approving the special inspection program. - ANS-The
building official
Who establishes the special inspection program? - ANS-The building department
What does the special inspection agreement state? - ANS-The owner or registered design
professional hired an approved special inspection agency
Who notifies the special inspector of upcoming inspection tasks? - ANS-The contractor