What determines when a Policies
Feature is ready to move
to the next column in the
Program Kanban?
Policies
Work in process (WIP)
limits
Definition of done
Definition of ready
Which two sources are Agile Teams
most likely to help when Customer feedback
creating a compelling
product Vision? (Choose
two.)
Agile Teams
Customer feedback
Competitor analysis
Stakeholder analysis
Team Backlogs
https://quizlet.com/1051587427/safe-apm-exam-prep-complete-exam-questions-and-accurate-answers-already-passed-flash-cards/?new 1/40
,6/5/25, 11:23 AM SAFe APM Exam Prep COMPLETE EXAM QUESTIONS AND ACCURATE ANSWERS |ALREADY PASSED!! Flashcards | Quizlet
Which aspect of whole- Augmented product
product thinking captures
a Customer's price
sensitivity?
Augmented product
Expected product
Potential product
Generic product
To foster alignment during PO sync
the PI execution, the
Product Manager may
often be asked to facilitate
which event in the closed
loop system?
PO sync
Scrum of Scrums
System Demo
Inspect & Adapt
What are the key elements Specifications, designs, and tests
of the Solution Intent?
Specifications, designs,
and tests
Strategic Themes and
nonfunctional
requirements
Epics, Features, and
Stories
Customer segments and
product Vision
https://quizlet.com/1051587427/safe-apm-exam-prep-complete-exam-questions-and-accurate-answers-already-passed-flash-cards/?new 2/40
,6/5/25, 11:23 AM SAFe APM Exam Prep COMPLETE EXAM QUESTIONS AND ACCURATE ANSWERS |ALREADY PASSED!! Flashcards | Quizlet
Which horizon describes Horizon 1
the desired state as stable
solutions that deliver high
value with minimal new
investment?
Horizon 1
Horizon 0
Horizon 2
Horizon 3
What are two outputs of a Committed PI Objectives
PI Planning event? Program Board with Dependencies
(Choose two.)
Top 10 Features
PI retrospective action
items
Committed PI Objectives
Program Board with
Dependencies
10-15% allocation to the
Architectural Runway
What does the Solution The environment in which the Solution operates
Context describe?
The behavior of the
Solution
The type of Solution the
Customer will use
The environment in which
the Solution operates
The Customer segment for
the Solution
https://quizlet.com/1051587427/safe-apm-exam-prep-complete-exam-questions-and-accurate-answers-already-passed-flash-cards/?new 3/40
, 6/5/25, 11:23 AM SAFe APM Exam Prep COMPLETE EXAM QUESTIONS AND ACCURATE ANSWERS |ALREADY PASSED!! Flashcards | Quizlet
Who are the three main Release Train Engineer
stakeholders involved in
calculating a Feature's
weighted shortest job first
values? (Choose three.)
Release Train Engineer
Product Manager
System Architects
Scrum Master
System Team
Business Owners
Which ceremony tracks ART sync
the ART's progress
towards meeting the
Program Increment
objectives?
ART sync
Participatory budgeting
Portfolio minimum viable
product reviews
Weighted shortest job first
prioritization