100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

DBIA TEST EXAM|COMPLETE STUDY GUIDE WITH HIGH YIELD QUESTIONS AND 100% RIGHT/VERIFIED ANSWERS|ALREADY GRADED A|GET A PASS ON YOUR FIRST TRIAL

Rating
-
Sold
-
Pages
18
Grade
A
Uploaded on
04-06-2025
Written in
2024/2025

Project Delivery System - CORRECT ANSWERS.️️How team members are organized, establishes when parties engage, determines roles of parties, and determines sequence of design, procurement, and construction (db, cmar, dbb) Procurement Method - CORRECT ANSWERS.️️how team members are selected (QBS, best value, low price, sole source) contracting approach - CORRECT ANSWERS.️️how team members are paid (fp, gmp, cost reimbursement, target price, unit price) Design-Bid-Build (DBB) - CORRECT ANSWERS.️️linear, sequential process, A/E selected on qualifications, GC selected on low price, design is fully completed without input from GC, A/E acting in owner's interests, with a historically strong bond, process is well-established and understood construction manager at risk - CORRECT ANSWERS.️️similar org structure to DBB, construction manager selected by QBS or best value, contractor provides precon services, negotiated gmp contracting approach, open book estimating process, potential to fast track project, construction cost determined before design completed, potential issues over what is reasonably inferable from gmp design documents Design-Build - CORRECT ANSWERS.️️The owner contracts with one entity (a person or firm) to provide both design and construction services, designer and contractor have a direct contractual relationship, selected by QBS or best value, wide spectrum of contracting approaches and organizational structures, single point responsibility, owner does not manage designer, owner exposure to claims is significantly reduced engineer procure construct (epc) - CORRECT ANSWERS.️️similar to design build, in industrial and power generation sectors, systems and performance testing are central to scope, contractor will typically perform engineering with its in-house staff, owner has need for single point responsibility, contracts include plant and process performance guarantees, contract items include performance and schedule liquidated damages and limitations of liability Multiple Prime Contracting - CORRECT ANSWERS.️️owner contracts with multiple trade contractors, attributes are typically similar to dbb, owner's ability to schedule and coordinate the work Integrated Project Delivery (IPD) - CORRECT ANSWERS.️️multi-party agreement - all parties equal, QBS procurement and target pricing contract approach, private sector use (limited at this time), key: owner's ability to accept risk public-private partnership (p3) - CORRECT ANSWERS.️️Instead of government building and maintaining major infrastructure (such as highway, water treatment plant), build and maintenance is outsourced to a private company. Opposed by public sector unions. this is not considered a delivery system but its underlying approaches are delivery systems and typically use DB. multiple procurement and contracting approaches shift left - CORRECT ANSWERS.️️intense efforts to establish scope early in the process; drives early team formation to include key trade subcontractors; can enable big decisions to be made early, affect project outcomes at lowest cost, establish a need for co-location and collaboration, and compress time during concurrent design and construction traditional design build - CORRECT ANSWERS.️️typically two-phase best value procurement with lump sum contract; owner defines project requirements and scope of prescriptive work; use of performance-based technical requirements with limited prescriptive specifications progressive design build - CORRECT ANSWERS.️️design and price are progressively developed after the design-builder is under contract; final project cost and schedule commitment is not established as part of the selection process; two phases: preliminary services and final design and construction services criteria documents - CORRECT ANSWERS.️️describe the end result bridging documents - CORRECT ANSWERS.️️prescribes how to achieve the end result design bid build paradigm - CORRECT ANSWERS.️️prior to bidding, owner undertakes a process to design the project and all of its details to 100% complete plans and specs. the owner is therefore responsible for success or failure of details of the design, and warrants the sufficiency of design to the contractor. the owner is therefore liable to the contractor for any gaps between plans and specifications and owner's requirements for project performance

Show more Read less
Institution
DBIA
Course
DBIA










Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
DBIA
Course
DBIA

Document information

Uploaded on
June 4, 2025
Number of pages
18
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

STUDYSAGE



DBIA TEST EXAM|COMPLETE STUDY
GUIDE WITH HIGH YIELD QUESTIONS
AND 100% RIGHT/VERIFIED
ANSWERS|ALREADY GRADED A|GET A
PASS ON YOUR FIRST TRIAL
Project Delivery System - CORRECT ANSWERS.✔️✔️How team members are
organized, establishes when parties engage, determines roles of parties, and
determines sequence of design, procurement, and construction (db, cmar, dbb)


Procurement Method - CORRECT ANSWERS.✔️✔️how team members are
selected (QBS, best value, low price, sole source)


contracting approach - CORRECT ANSWERS.✔️✔️how team members are paid
(fp, gmp, cost reimbursement, target price, unit price)


Design-Bid-Build (DBB) - CORRECT ANSWERS.✔️✔️linear, sequential process, A/E
selected on qualifications, GC selected on low price, design is fully completed
without input from GC, A/E acting in owner's interests, with a historically strong
bond, process is well-established and understood


construction manager at risk - CORRECT ANSWERS.✔️✔️similar org structure to
DBB, construction manager selected by QBS or best value, contractor provides
precon services, negotiated gmp contracting approach, open book estimating
process, potential to fast track project, construction cost determined before
design completed, potential issues over what is reasonably inferable from gmp
design documents




SUCCESS

,STUDYSAGE


Design-Build - CORRECT ANSWERS.✔️✔️The owner contracts with one entity (a
person or firm) to provide both design and construction services, designer and
contractor have a direct contractual relationship, selected by QBS or best value,
wide spectrum of contracting approaches and organizational structures, single
point responsibility, owner does not manage designer, owner exposure to claims
is significantly reduced


engineer procure construct (epc) - CORRECT ANSWERS.✔️✔️similar to design
build, in industrial and power generation sectors, systems and performance
testing are central to scope, contractor will typically perform engineering with its
in-house staff, owner has need for single point responsibility, contracts include
plant and process performance guarantees, contract items include performance
and schedule liquidated damages and limitations of liability


Multiple Prime Contracting - CORRECT ANSWERS.✔️✔️owner contracts with
multiple trade contractors, attributes are typically similar to dbb, owner's ability
to schedule and coordinate the work


Integrated Project Delivery (IPD) - CORRECT ANSWERS.✔️✔️multi-party
agreement - all parties equal, QBS procurement and target pricing contract
approach, private sector use (limited at this time), key: owner's ability to accept
risk


public-private partnership (p3) - CORRECT ANSWERS.✔️✔️Instead of government
building and maintaining major infrastructure (such as highway, water treatment
plant), build and maintenance is outsourced to a private company. Opposed by
public sector unions. this is not considered a delivery system but its underlying
approaches are delivery systems and typically use DB. multiple procurement and
contracting approaches




SUCCESS

, STUDYSAGE


shift left - CORRECT ANSWERS.✔️✔️intense efforts to establish scope early in the
process; drives early team formation to include key trade subcontractors; can
enable big decisions to be made early, affect project outcomes at lowest cost,
establish a need for co-location and collaboration, and compress time during
concurrent design and construction


traditional design build - CORRECT ANSWERS.✔️✔️typically two-phase best value
procurement with lump sum contract; owner defines project requirements and
scope of prescriptive work; use of performance-based technical requirements
with limited prescriptive specifications


progressive design build - CORRECT ANSWERS.✔️✔️design and price are
progressively developed after the design-builder is under contract; final project
cost and schedule commitment is not established as part of the selection process;
two phases: preliminary services and final design and construction services


criteria documents - CORRECT ANSWERS.✔️✔️describe the end result


bridging documents - CORRECT ANSWERS.✔️✔️prescribes how to achieve the
end result


design bid build paradigm - CORRECT ANSWERS.✔️✔️prior to bidding, owner
undertakes a process to design the project and all of its details to 100% complete
plans and specs. the owner is therefore responsible for success or failure of
details of the design, and warrants the sufficiency of design to the contractor. the
owner is therefore liable to the contractor for any gaps between plans and
specifications and owner's requirements for project performance




SUCCESS
$21.49
Get access to the full document:

100% satisfaction guarantee
Immediately available after payment
Both online and in PDF
No strings attached

Get to know the seller
Seller avatar
STUDYSAGE

Get to know the seller

Seller avatar
STUDYSAGE Yale University
View profile
Follow You need to be logged in order to follow users or courses
Sold
3
Member since
1 year
Number of followers
0
Documents
1049
Last sold
6 months ago
SELLING NOTES ONLINE,,GET ALL YOUR STUDY MATERIALS,QUALITY DOCUMENTS FOR BETTER RESULTS

Welcome to my online store, where I offer a variety of high-quality study documents designed to help students excel in their studies. Whether you need notes, summaries, or exam preparation materials, you'll find resources tailored to different subjects and learning styles. My goal is to support your academic journey by providing accessible and effective study aids." offer a variety of high-quality study documents designed to help students excel in their studies. Whether you need notes, summaries, or exam preparation materials, you'll find resources tailored to different subjects and learning styles. My goal is to support your academic journey by providing accessible and effective study aids."

Read more Read less
0.0

0 reviews

5
0
4
0
3
0
2
0
1
0

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions