Written by students who passed Immediately available after payment Read online or as PDF Wrong document? Swap it for free 4.6 TrustPilot
logo-home
Document preview thumbnail
Preview 4 out of 32 pages
Exam (elaborations)

AIC Prep UH Exam Questions with correct Answers 2025/2026 A+ Graded 100% Verified

Document preview thumbnail
Preview 4 out of 32 pages

AIC Prep UH Exam Questions with correct Answers 2025/2026 A+ Graded 100% Verified

Content preview

AIC Prep UH Exam Questions with correct
Answers 2025/2026 A+ Graded 100%
Verified
A 'place concrete' activity requires the placement of 2080 cubic yards. If the individual
production rate is 2 cubic yards per work hour per person, with a 10-person crew and 8 hour
workday, how many days are needed to complete this activity?
a. 13
b. 26
c. 104
d. 130 - ANS-a. 13

A topographical map is a drawing showing?
a. Subsurface soil conditions
b. A general profile view of the site
c. Contour lines and elevations d. Cross sections along the length of the project - ANS-c.
Contour lines and elevations

The owner's rep observed substandard drywall patches on a general contractor's renovation
project. Which of the following should be the representative's first course of action?
a. Save items for punch list
b. Notify drywall finisher of the problem
c. Tell painter not to accept patched walls.
d. Notify general contractors superintend of problem - ANS-d. Notify general contractors
superintend of problem

Five Contractors are bidding part of a job with storm sewer, sanitary sewer, and water
distribution. Their bids are: Contractor 1 will do storm and water for $2000. Contractor 2 will do
storm for $1000. Contractor 3 will do sanitary and water for $12,000. Contractor 4 will do
sanitary for $7,000 Contractor 5 will do water for $7,000 What is the lowest price for the
complete job?
a. $7,000
b. $9,000
c. $13,000
d. $15,000 - ANS-b. $9,000

Which of the following can be identified from the initial schedule of values?
a. Vendors working on the project

,b. Contractors proposed breakdown of the project cost c. Profit margin of the applicant d.
Quality of work in place - ANS-b. Contractors proposed breakdown of the project cost

Who is primarily responsible for ensuring that contract documents comply with building codes?
a. Owner
b. Contractor
c. Building inspector
d. Architect design professional - ANS-d. Architect design professional

What method is used to calculate activity duration?
a. Daily production rate divided by plan quantity
b. Plan quantity divided by crew rate
c. Plan quantity divided by daily production rate
d. Plan quantity dived by labor unit cost - ANS-c. Plan quantity divided by daily production rate

The architect has approved the rerouting of an HVAC through concrete slabs in a building. To
insure that activities are coordinated, a meeting should be called by the field supervisor and the
a. HVAC subcontractor only
b. HVAC subcontractor and all other subcontractors
c. HVAC subcontractor and all other affected subcontractors
d. HVAC subcontractor and the architect engineer - ANS-c. HVAC subcontractor and all other
affected subcontractors

A project schedule has been updated. The activity placement of spread footing concrete was
originally scheduled to begin as early as day 10. The activity duration is 4 days. The actual start
day was day 12. The original schedule had calculated total float of 7 days for this activity. The
recalculated total float for the activity, when updated, would be
a. 2 days
b. 5 days
c. 6 days
d. 9 days - ANS-b. 5 days

10. Under a design-build contract which of the following parties is responsible for coordination of
the design engineers and the subcontractors
a. Owner
b. Contractor
c. Architect
d. Subcontractor - ANS-b. Contractor

Concrete to be poured for 10 footings are 5 feet wide by 5 feet long by 2 feet deep. How many
cubic yards of concrete should the estimate be for this pour, using a 10%waste factor.
a. 14.8
b. 16.3
c. 18.5

,d. 20.3 - ANS-d. 20.3

What is the term for a change order issued by the owner of a project that is outside of the
contractor's scope of work and therefore the contractor can a refuse to perform the work?
a. Cardinal Change
b. Preliminary Change
c. No cost change order
d. Supplemental instructions - ANS-a. Cardinal Change

What is a "Schedule of Values"? a. A list of ethical practices in which employees may participate
b. a table showing average wage rates for each crew
c. a breakdown of the contract amount into pay items
d. a list of construction activities - ANS-c. a breakdown of the contract amount into pay items

During layout of a site, it is determined that the slope distance between point A and point B is
200 feet at a slope angle of 15 degrees. What is the actual horizontal distance (H distance) on
the plans from point A to point B?
a. 181.26'
b. 193.19'
c. 199.44'
d. 207.06' - ANS-b. 193.19'

According to CSI, which of the following is in the project manual?
a. General requirements
b. Estimate
c. schedule
d. Certificate of occupancy - ANS-a. General requirements

Which of the following are calculated by the "Backward pass" through the CPM network?
a. Early start and late start
b. Total float and free float
c. Early start and early finish
d. Late start and late finish - ANS-d. Late start and late finish

Which of the following pre-bid information should be gathered for developing a bid proposal? a.
Schematic design, design development drawings, contract documents, project manual, and bid
documents
b. adjacent site conditions, existing surface conditions, existing utility locations, and field
dimensions
c. value engineering criteria, design outline specifications, total quality management procedures,
safety management procedures
d. shop drawings, product data sheets, samples, and submittal logs - ANS-a. Schematic
design, design development drawings, contract documents, project manual, and bid documents

, Subcontractor "A" submits shop drawings to the GC which include materials that do not comply
with the contract documents. The GC as well as the architect stamps all of them "reviewed". The
materials are then shipped to the job site. During an off-loading inspection, the GC notices the
noncompliance. What action should the GC take concerning the matter?
a. install them because the architect's stamp is a variance to the contract document
b. install them and ask for a discount from the subcontractor c. accept and install materials
d. reject the shipment and require compliance with the contract documents - ANS-d. reject the
shipment and require compliance with the contract documents

Which of the following incorporates the tracking, confirming, and accelerating of delivery of an
item that has been purchased?
a. Routing
b. Expediting
c. Monitoring
d. Controlling - ANS-b. Expediting

How should a constructor establish the field staffing for a project?
a. in consultation with the architect and the owner
b. in Conformance with OSHA and ADA requirements
c. By reference to a cost manual
d. by utilization of past experience and schedule requirements - ANS-d. by utilization of past
experience and schedule requirements

if a schedule is accelerated, which of the following activities must be focused on first? a. Critical
activities b. Non critical Activities c. all activities with float time d. all activities with the least costs
- ANS-a. Critical activities

Which of the following provides the highest strength to dimensional lumber?
a. moisture content
b. age of wood
c. grain orientation
d. knots - ANS-c. grain orientation

Which of the following has the highest priority after a discovery on a Monday morning that the
job site has been vandalized and the magazine cases have been emptied of explosives?
a. Call the insurance agent to see if damage is covered
b. Call the police to initiate an investigation
c. Pull the records on explosives stored on the site
d. Begin cleanup and repair the damage - ANS-b. Call the police to initiate an investigation

What is the point in the project when the architect has determined that the facility or a portion of
the facility is acceptable for owner use and occupancy?
a. Substantial completion date
b. Facility completion date

Document information

Uploaded on
June 4, 2025
Number of pages
32
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers
$15.99

Wrong document? Swap it for free Within 14 days of purchase and before downloading, you can choose a different document. You can simply spend the amount again.
Written by students who passed
Immediately available after payment
Read online or as PDF

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
annlinsey
3.0
(4)
Sold
26
Followers
0
Items
699
Last sold
4 weeks ago



Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Working on your references?

Create accurate citations in APA, MLA and Harvard with our free citation generator.

Working on your references?

Frequently asked questions