100% satisfaction guarantee Immediately available after payment Both online and in PDF No strings attached 4.2 TrustPilot
logo-home
Exam (elaborations)

PTP MODULE 2 EXAM QUESTIONS & ANSWERS

Rating
-
Sold
-
Pages
15
Grade
A+
Uploaded on
31-05-2025
Written in
2024/2025

PTP MODULE 2 EXAM QUESTIONS & ANSWERS

Institution
PTP
Course
PTP









Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
PTP
Course
PTP

Document information

Uploaded on
May 31, 2025
Number of pages
15
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

PTP MODULE 2 EXAM QUESTIONS & ANSWERS

How many days after a foundation is poured should you wait before backfilling? -
Answers :7 days is safe (28 days is ideal, but unrealistic)

What phases need to be completed before the backfill? - Answers :-Waterproofing
- Drain Tile
- Foundation / Footers

What is rebar? - Answers :Steel bar used as tension device set inside the concrete form
to reinforce concrete strength

How is rebar measured? - Answers :By eighths

In relation to the thickness of the footing, where should rebar be placed? - Answers
:Installed at the bottom third of the footing

What is a stanchion pad? - Answers :A concrete pier used to support a stanchion post
or steel "lolly" column

How do you determine the size (dimensions) of a stanchion pad? - Answers
:Foundation plans or check blueprints (minimum thickness is 12")

Frost Footing - Answers :Footing used in low grade condition which extends below the
depth that the ground will freeze

Spread or Floater Footing - Answers :- An unformed footer used when poor soil
conditions exist
- Larger depth and width
- Uses rebar

Conventional Footing - Answers :A 4"x4" trenched and formed footer

Pinning a Footing - Answers :- To pin point side of house with spray-paint
- Or giving more support to a footer so it doesn't shift

What are some items that should be marked on the footing/foundation plan for the
footing contractor? - Answers :- Sleeves
- Rebar hooks for wall bracing
- Elevation
- Frost footing location
- Stanchion Pads

Describe a Frost Line - Answers :The area below grade in which the ground freezes;
requires frost footings

, What is the minimum frost line in your area? - Answers :2'

What are some indications or conditions that may necessitate a change to the normal
footing? - Answers :- Bad ground change
- Code changes

Within what time frame should be the footing material be removed? - Answers :24 hours

Where should any excess concrete be unloaded? - Answers :On 10 mil poly and
returned to concrete plant

What is a keyway, and what size should it be? - Answers :A notch or groove in a footer
or poured wall designed to provide a channel for the concrete to tie into. 1 1/2" deep by
3 1/2" wide

Describe the process used to "lay out" a footing using the excavation hubs - Answers
:Measure from the stake to the pin in the footer

How would you determine if a footing is square? - Answers :Diagnonals

How would you determine if a footing is level? - Answers :Builder's level or laser level

What are the maximum tolerances for a footing? - Answers :Out of square: 1/2"
Out of level: 1/4"
Dimensional: 1/2"

Excavator - Answers :- AKA Track Hoe
- Dig holes/trenches quickly
- Best with digging holes and loading trucks for hauling

Track Loader - Answers :Good at moving large amount of dirt; not ideal for small areas

Bobcat - Answers :Utility type machine able to attach many things to move, dig, crush,
material etc...

Bulldozer - Answers :Machine with metal plow used to push various materials for
grading, moving dirt, etc...

What should you do with topsoil that is on the lot? - Answers :Scrape it off and save it
for grading after backfill

Why is it important to use clean fill for a backfill? - Answers :- Could cause voids or
damage to your draintile or waterproofing
- Could include radon or methane

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
GEEKA YALA UNIVERSITY
View profile
Follow You need to be logged in order to follow users or courses
Sold
1998
Member since
3 year
Number of followers
1444
Documents
46903
Last sold
4 days ago

3.8

342 reviews

5
170
4
61
3
44
2
16
1
51

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their tests and reviewed by others who've used these notes.

Didn't get what you expected? Choose another document

No worries! You can instantly pick a different document that better fits what you're looking for.

Pay as you like, start learning right away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and aced it. It really can be that simple.”

Alisha Student

Frequently asked questions