a. It shall be commensurate with all of the same
authority granted to the contracting officer
Which statement is true b.It shall be designated in writing, with a copy given to
regarding the authority of a the contractor and contract administration office ✅
contracting officer's c. It shall be given verbally by the contracting officer only on a
representative (COR)? case-by-case basis
d. It shall be granted by the program office once the
COR has been designated by the contracting officer
Which term means the total a. Total costs of ownership
cost to the government of b. Life cycle costs ✅
c. True program costs
acquiring, operating,
d. Total costs of management
supporting, and (if applicable)
disposing of the items being
acquired?
Obtain written assurance from the responsible FISCAL
a.
AUTHORITY that adequate funds are available ✅
It is the government's
b. Obtain written assurance from the paying office that adequate
policy that before funds are available
executing a contract, c. Confirm that the Appropriations Bills has passed
the contracting d. Obtain written assurance from the head of the
officer must do what? contracting office that adequate funds are available
a. Purchase the requirement as a noncommercial item
What would be the
b. Purchase the requirement as a commercial item ✅
preferred way to acquire
c. Purchase the items as another transactional authority acquisition
an item in government
d. Purchase the item as a developmental item
contracting?
a. They are read by the briefer
In briefing pre-negotiation
b. They are filled with text
objectives for approval,
c. The are extremely colorful
what should contracting
d. They are simple and concise ✅
c9-40c0-8ecb-b412d144884c 1/23
,5/24/25, 10:36 AM FAC-C Pre-Exam Solved 100% Correct
officers ensure regarding
their briefing slides?
Government contract a. Variable-costcontracts
types are grouped into two b. Cost-reimbursement contracts ✅
broad categories. This c. Cost contracts
d. Undefinitized contracts
includes fixed-price
contracts and what
other
contract category?
When should acquisition As soon as the agency need is identified
planning begin?
a. By motivating contractor efforts that might not otherwise be
emphasized ✅
How are incentive contracts
b. By ensuring contractors meet minimum requirements
designed to obtain specific c. By allowing the government to meet funding objectives
acquisition objectives? d. By addressing fluctuations in market conditions
a. The
overall benefit to the acquisition significantly
Contracting officers shall outweighs the increased cost of administration ✅
provide property to b. The contractor requests the use of government property
contractors only when c. Government property is available
d. The contractor is unwilling to supply its own resources
what is clearly
demonstrated?
a. Encourage small businesses to subcontract to large businesses
b. Bundle or consolidate acquisitions
The contracting officer shall
c. Abbreviate delivery schedules to decrease the
take which of the following
likelihood of large businesses proposing
actions to encourage small
d. Divide acquisitions into reasonably small lots to
business participation in permit offers on quantities less than the total
acquisitions? requirement ✅
a. Adequate price competition ✅
b. Sole source acquisition
Which of the following is an
c. Subcontractor contracts
exception to obtaining
d. Noncommercial item
certified cost or pricing
data?
c9-40c0-8ecb-b412d144884c 2/23
, 5/24/25, 10:36 AM FAC-C Pre-Exam Solved 100% Correct
To the maximum extent a. Essential physical characteristics ✅
b. Commerciality
practicable, acquisition
c. Requiring activity preference
officials shall state
d. Availability
requirements of supplies or
services in terms of
functions to be performed,
performance required,
or:
a. Unless they are used with more than one alternate, then full text
Provisions and clauses should is required
be b. To the maximum practical extent, rather than being
incorporated by reference in incorporated in full text ✅
c. Unless they contain a blank within the text that the
solicitations and contracts:
contracting officer must fill in prior to award
d. Unless the uniform contract format (UCF) applies
a. All parties in the competitive range
Which offerors receive an b. None. Solicitations are modified, not amended.
amendment on a solicitation c. All parties receiving the solicitation ✅
that has yet to close? d. None. Solicitations can't be amended until they have closed
a. Always obtain the lowest price for government requirements
What is the purpose of b. Find a sole source contractor to meet the government's
exchanging requirements
information with industry c. Negotiate the best deal in response to the government's
before receipt of requirements
d. Improve the understanding of government requirements and
proposals?
industry capabilities
✅
When using FAR part 12 a. Management plans
procedures, the technical b. Manufacturing plans
evaluation would c. Quality assurance plans
d. Warranty provisions ✅
normally
include examination of
such things as product
literature, product
samples (if requested),
technical features, and:
a. In the same manner for all acquisitions for consistency purposes
Which statement is true b. Only if unsure of adequate competition
c. Appropriate to the circumstances ✅
c9-40c0-8ecb-b412d144884c 3/23