Construction FE Civil Questions with Detailed
Verified Answers (100% Correct Answers) /Already
Graded A+
Is the most traditional project delivery method and appeals to those
looking for low-cost bids. In this method, the owner contracts designers
and builders separately.
Ans: Design-bid-build
is a construction project delivery method where the designer and
builder work together under a single contract from the beginning of the
project in order to ensure unity and collaboration throughout the
process.
Ans: Design- build
Select all that clearly demonstrate an advantage of the Design-Build
project delivery over the Design-Bid-Build approach:
- There is single point of contractual responsibility for the owner for the
entire project
-There are contractual relationships with the Owner that prevent a
conflict of interest
-The design is clearly and explicitly defined at the outset of the project
Sunday, 02 March 2025
,- The design includes significant collaboration between the Engineer
and the Contractor
-The schedule can be fast-tracked and construction can begin before
the complete project design is finalized
- The Owner will receive a project at the lowest competitive cost
Ans: There is single point of contractual responsibility for the owner for the
entire project
There is single point of contractual responsibility for the owner for the entire
project
The schedule can be fast-tracked and construction can begin before the
complete project design is finalized
An indemnification clause in an engineer's design contract is typically
tied to:
A. Negligent engineering design
B. Claims submitted by parties affected by a failure
C. Project cost overruns
D. Improper construction methods by the Contractor
Ans: A. Negligent engineering design
Examstudy - Stuvia US
,Collusion on a construction project typically refers to which of the
following?
A. A practice where multiple contractors conspire to fix prices or rig
bids
B. A system where public officials receive money from the contractor
after award
C. Falsely increasing the price of change order
D. Misrepresenting the amount of work that has been completed to get
advance payments
Ans: A. A practice where multiple contractors conspire to fix prices or rig
bids
A preconstruction conference should be he held:
A. Prior to advertising for bids
B. After advertising for bids but before bids are received
C. After bid opening but before award of the contract
D. After execution of an agreement but before Notice to Proceed
Ans: D. After execution of an agreement but before Notice to Proceed
Types of submittals for engineer approval typically include all the
following except:
Examstudy - Stuvia US
, A. Product data
B. Shop drawings
C. Installation means and methods
D. Mill certificates
Ans: C. Installation means and methods
Which of the following statements best define what is meant by
"substantial completion" with respect to a construction contract?
A. Project can be used and occupied by the owner and is completely
finished B. Project can be used and occupied by the owner but there is
still a punch-list of minor work remaining
C. Contractor's performance bond will be used to finish the remaining
work
D. The owner has received a final release of liens from all
subcontractors
Ans: B. Project can be used and occupied by the owner but there is still a
punch-list of minor work remaining
a financial guarantee that the terms of a contract will be honored. If
one party to a contract cannot complete their obligations, the bond is
paid out to the other party to compensate for their damages or costs.
Ans: Performance bond