U3 ICC Tank Tightness Testing WY Study
Set for U3 Exam Questions with 100%
complete solutions
Terms in this set (169) Original
| | | | |
cathodic protection systems can influence other nearby | | | | | |
metallic structures that are not part of the protected system.
| | | | | | | | | |
Impressed-current
and fittings are used to separate buried piping from | | | | | | | |
above ground piping and tanks from piping.
| | | | | | |
Dielectric bushings |
On a steel tank without cathodic protection, if a coating is flawed, what happens at
| | | | | | | | | | | | | |
the flaw?
| |
a. Cathodic surface is increased | | |
b. Current flow is increased from this area | | | | | |
c. Current flow is increased to this area | | | | | |
b. Current flow is increased from this area
| | | | | | |
On an impressed current cathodic protection system, the negative wire of the
| | | | | | | | | | |
rectifier is connected to the:
| | | | |
a. Anode
,b. Cathode
c. Drop tube |
d. Dielectric union |
b. Cathode
|
All are examples of acceptable release detection for tanks, except:
| | | | | | | | |
a. Impressed current cathodic protection | | |
b. Automatic tank gauging | |
c. Statistical inventory reconciliation | |
d. Soil-vapor monitoring |
a. Impressed current cathodic protection | | |
When a tank is temporarily closed, the cathodic protection system:
| | | | | | | | |
a. Must be turned off | | |
b. Must remain in operation
| | |
c. Should be removed | |
d. Operator can have it on or off. | | | | | |
b. Must remain in operation
| | |
When a steel tank is installed with a galvanic CP system attached, the tank
| | | | | | | | | | | | |
gauges are usually connected through a riser with a dielectric bushing. What is
| | | | | | | | | | | | |
the purpose of that?
| | | |
a. To prevent static discharge
| | |
b. To minimize effects of noise
| | | |
c. To electrically isolate the tank from the tank gauge
| | | | | | | |
d. To prevent water intrusion in the tank
| | | | | |
c. To electrically isolate the tank from the tank gauge
| | | | | | | |
Factory-installed diectric coatings may include all of the following except: | | | | | | | | |
,a . Asphalt
| |
b. epoxies
c. Enamels
d. fiberglass-reinforced plastic |
a . Asphalt
| | |
According to the EPA, Tank tightness test data must be maintained for:
| | | | | | | | | | |
a. 18 months |
b. 3 years |
c. 5 years |
d. Until the next test is performed | | | | |
d. Until the next test is performed
| | | | | |
How long must records of UST system repairs be available on site?
| | | | | | | | | | |
a. 60 days |
b. 1 year |
c. 5 years |
d. for the remaining lifetime of the UST system
| | | | | | |
d. for the remaining lifetime of the UST system
| | | | | | | |
In the event of a release, what is the reporting requirement?
| | | | | | | | | |
a. ICC licensed supervisor must report the leak within 24 hours
| | | | | | | | |
b. Owner/Operator must report the leak within 24 hours | | | | | | |
c. Owner/Operator must report the leak within 18 hours | | | | | | |
d. ICC licensed supervisor must report the leak within 18 hours
| | | | | | | | |
b. Owner/Operator must report the leak within 24 hours
| | | | | | | |
At what size spill does it need to be reported?
| | | | | | | | |
a. 5 gallons |
, b. 10 gallons |
c. 15 gallons |
d. 25 gallons |
d. 25 gallons
| |
Contamination of soils is encountered before removing a tank. The clean up must | | | | | | | | | | | |
be initiated by the:
| | | |
a. Fire Marshal |
b. Ecology inspector |
c. Owner / operator of the UST system | | | | | |
d. Landlord
c. Owner / operator of the UST system
| | | | | | |
All are examples of overfill protection, except:
| | | | | |
a. Vent restricting device | |
b. Drop tube with an automatic shut off device
| | | | | | |
c. Audible and visual alarm | | |
d. Expandable bladder in manway | | |
d. Expandable bladder in manway
| | | |
Definition: An observation well is located: | | | | |
a. Outside the tank excavation, but within 25 feet | | | | | | |
b. Inside the tank excavation, extending 1' below the bottom of the tanks
| | | | | | | | | | |
c. Inside the tank excavation, no deeper than 15 feet
| | | | | | | |
d. Outside the tank excavation until ground water is reached
| | | | | | | |
b. Inside the tank excavation, extending 1' below the bottom of the tanks
| | | | | | | | | | | |
A monitoring well lid is marked with a:
| | | | | | |
a. Black lid with a white equilateral triangle
| | | | | |
Set for U3 Exam Questions with 100%
complete solutions
Terms in this set (169) Original
| | | | |
cathodic protection systems can influence other nearby | | | | | |
metallic structures that are not part of the protected system.
| | | | | | | | | |
Impressed-current
and fittings are used to separate buried piping from | | | | | | | |
above ground piping and tanks from piping.
| | | | | | |
Dielectric bushings |
On a steel tank without cathodic protection, if a coating is flawed, what happens at
| | | | | | | | | | | | | |
the flaw?
| |
a. Cathodic surface is increased | | |
b. Current flow is increased from this area | | | | | |
c. Current flow is increased to this area | | | | | |
b. Current flow is increased from this area
| | | | | | |
On an impressed current cathodic protection system, the negative wire of the
| | | | | | | | | | |
rectifier is connected to the:
| | | | |
a. Anode
,b. Cathode
c. Drop tube |
d. Dielectric union |
b. Cathode
|
All are examples of acceptable release detection for tanks, except:
| | | | | | | | |
a. Impressed current cathodic protection | | |
b. Automatic tank gauging | |
c. Statistical inventory reconciliation | |
d. Soil-vapor monitoring |
a. Impressed current cathodic protection | | |
When a tank is temporarily closed, the cathodic protection system:
| | | | | | | | |
a. Must be turned off | | |
b. Must remain in operation
| | |
c. Should be removed | |
d. Operator can have it on or off. | | | | | |
b. Must remain in operation
| | |
When a steel tank is installed with a galvanic CP system attached, the tank
| | | | | | | | | | | | |
gauges are usually connected through a riser with a dielectric bushing. What is
| | | | | | | | | | | | |
the purpose of that?
| | | |
a. To prevent static discharge
| | |
b. To minimize effects of noise
| | | |
c. To electrically isolate the tank from the tank gauge
| | | | | | | |
d. To prevent water intrusion in the tank
| | | | | |
c. To electrically isolate the tank from the tank gauge
| | | | | | | |
Factory-installed diectric coatings may include all of the following except: | | | | | | | | |
,a . Asphalt
| |
b. epoxies
c. Enamels
d. fiberglass-reinforced plastic |
a . Asphalt
| | |
According to the EPA, Tank tightness test data must be maintained for:
| | | | | | | | | | |
a. 18 months |
b. 3 years |
c. 5 years |
d. Until the next test is performed | | | | |
d. Until the next test is performed
| | | | | |
How long must records of UST system repairs be available on site?
| | | | | | | | | | |
a. 60 days |
b. 1 year |
c. 5 years |
d. for the remaining lifetime of the UST system
| | | | | | |
d. for the remaining lifetime of the UST system
| | | | | | | |
In the event of a release, what is the reporting requirement?
| | | | | | | | | |
a. ICC licensed supervisor must report the leak within 24 hours
| | | | | | | | |
b. Owner/Operator must report the leak within 24 hours | | | | | | |
c. Owner/Operator must report the leak within 18 hours | | | | | | |
d. ICC licensed supervisor must report the leak within 18 hours
| | | | | | | | |
b. Owner/Operator must report the leak within 24 hours
| | | | | | | |
At what size spill does it need to be reported?
| | | | | | | | |
a. 5 gallons |
, b. 10 gallons |
c. 15 gallons |
d. 25 gallons |
d. 25 gallons
| |
Contamination of soils is encountered before removing a tank. The clean up must | | | | | | | | | | | |
be initiated by the:
| | | |
a. Fire Marshal |
b. Ecology inspector |
c. Owner / operator of the UST system | | | | | |
d. Landlord
c. Owner / operator of the UST system
| | | | | | |
All are examples of overfill protection, except:
| | | | | |
a. Vent restricting device | |
b. Drop tube with an automatic shut off device
| | | | | | |
c. Audible and visual alarm | | |
d. Expandable bladder in manway | | |
d. Expandable bladder in manway
| | | |
Definition: An observation well is located: | | | | |
a. Outside the tank excavation, but within 25 feet | | | | | | |
b. Inside the tank excavation, extending 1' below the bottom of the tanks
| | | | | | | | | | |
c. Inside the tank excavation, no deeper than 15 feet
| | | | | | | |
d. Outside the tank excavation until ground water is reached
| | | | | | | |
b. Inside the tank excavation, extending 1' below the bottom of the tanks
| | | | | | | | | | | |
A monitoring well lid is marked with a:
| | | | | | |
a. Black lid with a white equilateral triangle
| | | | | |