U3 ICC Tank Tightness Testing Exam Questions
and Answers
On a steel tank without cathodic protection, if a coating is flawed, what
| | | | | | | | | | | |
happens at the flaw?
| | | |
a. Cathodic surface is increased
| | | |
b. Current flow is increased from this area
| | | | | | |
c. Current flow is increased to this area - correct answers ✅b. Current flow
| | | | | | | | | | | | |
is increased from this area
| | | | |
On an impressed current cathodic protection system, the negative wire of
| | | | | | | | | |
the rectifier is connected to the:
| | | | | |
a. Anode
|
b. Cathode
|
c. Drop tube
| |
d. Dielectric union - correct answers ✅b. Cathode
| | | | | | |
All are examples of acceptable release detection for tanks, except:
| | | | | | | | |
a. Impressed current cathodic protection
| | | |
,b. Automatic tank gauging
| | |
c. Statistical inventory reconciliation
| | |
d. Soil-vapor monitoring - correct answers ✅a. Impressed current cathodic
| | | | | | | | |
protection
|
When a tank is temporarily closed, the cathodic protection system:
| | | | | | | | |
a. Must be turned off
| | | |
b. Must remain in operation
| | | |
c. Should be removed
| | |
d. Operator can have it on or off. - correct answers ✅b. Must remain in
| | | | | | | | | | | | | |
operation
|
When a steel tank is installed with a galvanic CP system attached, the tank
| | | | | | | | | | | | |
gauges are usually connected through a riser with a dielectric bushing. What
| | | | | | | | | | | |
is the purpose of that?
| | | | |
a. To prevent static discharge
| | | |
b. To minimize effects of noise
| | | | |
c. To electrically isolate the tank from the tank gauge
| | | | | | | | |
, d. To prevent water intrusion in the tank - correct answers ✅c. To
| | | | | | | | | | | |
electrically isolate the tank from the tank gauge
| | | | | | | |
Factory-installed diectric coatings may include all of the following except:
| | | | | | | | |
a . Asphalt
| |
b. epoxies
|
c. Enamels
|
d. fiberglass-reinforced plastic - correct answers ✅a . Asphalt
| | | | | | | |
According to the EPA, Tank tightness test data must be maintained for:
| | | | | | | | | | |
a. 18 months
| |
b. 3 years
| |
c. 5 years
| |
d. Until the next test is performed - correct answers ✅d. Until the next test
| | | | | | | | | | | | | |
is performed
| |
How long must records of UST system repairs be available on site?
| | | | | | | | | | |
a. 60 days
| |
and Answers
On a steel tank without cathodic protection, if a coating is flawed, what
| | | | | | | | | | | |
happens at the flaw?
| | | |
a. Cathodic surface is increased
| | | |
b. Current flow is increased from this area
| | | | | | |
c. Current flow is increased to this area - correct answers ✅b. Current flow
| | | | | | | | | | | | |
is increased from this area
| | | | |
On an impressed current cathodic protection system, the negative wire of
| | | | | | | | | |
the rectifier is connected to the:
| | | | | |
a. Anode
|
b. Cathode
|
c. Drop tube
| |
d. Dielectric union - correct answers ✅b. Cathode
| | | | | | |
All are examples of acceptable release detection for tanks, except:
| | | | | | | | |
a. Impressed current cathodic protection
| | | |
,b. Automatic tank gauging
| | |
c. Statistical inventory reconciliation
| | |
d. Soil-vapor monitoring - correct answers ✅a. Impressed current cathodic
| | | | | | | | |
protection
|
When a tank is temporarily closed, the cathodic protection system:
| | | | | | | | |
a. Must be turned off
| | | |
b. Must remain in operation
| | | |
c. Should be removed
| | |
d. Operator can have it on or off. - correct answers ✅b. Must remain in
| | | | | | | | | | | | | |
operation
|
When a steel tank is installed with a galvanic CP system attached, the tank
| | | | | | | | | | | | |
gauges are usually connected through a riser with a dielectric bushing. What
| | | | | | | | | | | |
is the purpose of that?
| | | | |
a. To prevent static discharge
| | | |
b. To minimize effects of noise
| | | | |
c. To electrically isolate the tank from the tank gauge
| | | | | | | | |
, d. To prevent water intrusion in the tank - correct answers ✅c. To
| | | | | | | | | | | |
electrically isolate the tank from the tank gauge
| | | | | | | |
Factory-installed diectric coatings may include all of the following except:
| | | | | | | | |
a . Asphalt
| |
b. epoxies
|
c. Enamels
|
d. fiberglass-reinforced plastic - correct answers ✅a . Asphalt
| | | | | | | |
According to the EPA, Tank tightness test data must be maintained for:
| | | | | | | | | | |
a. 18 months
| |
b. 3 years
| |
c. 5 years
| |
d. Until the next test is performed - correct answers ✅d. Until the next test
| | | | | | | | | | | | | |
is performed
| |
How long must records of UST system repairs be available on site?
| | | | | | | | | | |
a. 60 days
| |